Difference between revisions of "Daily Activities"

From LCLS-II testing
Jump to navigation Jump to search
Line 1: Line 1:
 +
10/27/2017 - 3 of the 6 vacuum connections for the CEBAF style cryomodules have been secured
 +
 
10/26/2017 - The downstream side of zone 2 has gone through the 'slow' bleed-up process
 
10/26/2017 - The downstream side of zone 2 has gone through the 'slow' bleed-up process
  

Revision as of 09:34, 27 October 2017

10/27/2017 - 3 of the 6 vacuum connections for the CEBAF style cryomodules have been secured

10/26/2017 - The downstream side of zone 2 has gone through the 'slow' bleed-up process

10/25/2017 - Vacuum has been secured from the upstream side of Zone 2 CM in the vault

10/24/2017 - 480 VAC panels are being mounted in gallery

10/11/2017 - Waveguide design review

10/10/2017 - Clean Hoods have been moved to vault

10/9/2017 - Electricians have "Air Gapped" all power connections to FL03 & FL04 CPS & HPAs