2/6/2018 - PSS chassis wiring nearly complete for zone 3 (CM #1) [1], AC power run to SSAs in zone 3 [2]

2/5/2018 - Magnet water lines have been moved out of the way of waveguide installation

2/4/2018 - Fly Eagles Fly! Congrats on Super Bowl victory!

2/2/2018 - Solid State Amplifiers are being positioned in the gallery [3], Waveguide installation has begun in the tunnel [4]

2/1/2018 - Radiation assessment complete [5], SSAs are craned into gallery, 19 pin & 8 pin connectors have been delivered

1/31/2018 - Happy Super Blue Blood Moon! Installation crew has completed waveguide support structure

1/30/2018 - Servers installed in the gallery racks, 100% of waveguide strait sections have been delivered, an update on the project status was presented to the joiont call [6]

1/29/2018 - First racks are powered up in gallery

1/26/2018 - CryoCon temperature controllers have been delivered [7], server rack has power, 450 Waveguide gaskets were delivered [8], all 4 pin connectors were delivered [9]

1/25/2018 - Installation crew began drilling holes, mounting anchors, and unistrut for waveguide installation. [10], I hosted a tour for the SLAC folks, Excess cable was inventoried in transport trailers

1/24/2018 - PDFs of waveguide layout is posted [11] [12] [13], Survey is finished with waveguide support layout in the vault, clean room ordered for making center connection between CMs [14]

1/23/2018 - I hosted Elvin Harms for a visit, survey crew is marking vault ceiling for the waveguide supports, racks were jacked up

1/22/2018 - Waveguide deliveries have been inventoried and separated out to the gallery & vault locations, 8 more SSAs were delivered

1/19/2018 - MS connectors for CMs have been ordered, AC power work continues

1/18/2018 - More waveguide delivered, rack ready for jacking, threaded rod support for waveguide layout being surveyed

1/17/2018 - New AC panel mounted next to E1000, this will supply 120 VAC for all new racks and equipment.

1/16/2018 - Cryomodule in zone 2 is being surveyed into place.

1/15/2018 - Happy MLK Day!

1/12/2018 - Waveguide supports have been installed in both zones [15], PSS box mounted

1/11/2018 - Ac Power requirements have been posted [16], the rack prep is complete - they are ready to be jacked up, Dark Light power supply moved to west side door for extraction.

1/10/2018 - Klystron racks are ready to be jacked up

1/4/2018 - Happy Snow Day 8 !

12/22/2017 - C37 moved back into place completing the shuffle! (placed 'order' with C. Curtis for final alignment...) [17]

12/21/2017 - Began placing orders for Cryogenic controls and Vacuum system cables

12/19/2017 - Rack bases were delivered

12/18/2017 - Zone 2 base plates have been grouted this AM [18], CryoCon 18i cryodiode controllers have been ordered [19], PC/PLC installed and communicating [20]

12/15/2018 - Clean room draft design sent to manufacturer for quote [21], Dell servers have been delivered!

12/14/2017 - Third review was held for the cryo-Can assembly that ties the CMs to the cryo transfer lines Mounting base plates have been relocated, and surveyed in for C37, zone 2. These are ready to re-grout. PCs are ready for installation & network connection - these are remote accessed machines with no local keyboard & monitor

12/13/2017 - PCs arrived for PLC remote programming, PLC arrived from SLAC to be programed

12/12/2017 - Nuts & bolts for waveguide installation have been delivered

12/6/2017 - Wheels are attached to zone 3 for movement to south wall for storage

12/5/2017 - Girder 1F04 removed for ease of CM move, waveguide gaskets ordered

12/4/2017 - Zone 4 klystrons removed

11/28/2017 - JLab electricians have been trained to remove Klystrons

11/22/2017 - 7/8" Heliax for Total Loss Monitor delivered

11/21/2017 - Waveguide order awarded

11/20/2017 - Waveguide order tweaked to reflect delivery times for SLAC type mitered H & E bends vs standard parts

11/17/2017 - Kevin visited Mega Ind., the waveguide company

11/15/2017 - 7/8" Heliax ordered for Total Loss Monitor (TLM)

11/14/2017 - Heliax PR submitted - 6,000' 3/8"

11/13/2017 - Second Cryo Can design review [22]

11/10/2017 - Waveguide bids have been received

11/9/2017 - Network switch installed and operational in Zone 3 FL03B13

11/8/2017 - Kevin visiting FermiLab - discussions with OPs, CM Assembly, Interlock group & others

11/7/2017 - Semi-annual Personnel Safety System re-certification complete

11/6/2017 - Draft P & ID drawing done & posted [23]

11/3/2017 - GW magnets were radcon surveyed and moved to storage in BLDG 36, 2 PCs were ordered for PLC programming of Cryo controls & vacuum controls, service request submitted to move rack from free stock to LERF gallery - this is a 36" deep rack for the servers (& free {;-), the network has been created for the project; lclsnet - [24], Active VVUs have been installed on 480 VAC panels [25]

11/2/2017 - All of the girders have been removed in preparation of CM move & shuffle [[26]]

11/1/2017 - Last of the cryomodule vacuums & girders have been secured & the clean room has been removed from the vault, the cryomodule & waveguide layout has been taped out on vault floor [[27]]

10/31/2017 - Cable length & routing checks being made

10/30/2017 - Network switches ordered, 2 racks moved to gallery, cryomodule vacuum isolation continues

10/27/2017 - 3 of the 6 vacuum connections for the CEBAF style cryomodules have been secured, had a cable planning meeting

10/26/2017 - The downstream side of zone 2 has gone through the 'slow' bleed-up process

10/25/2017 - Vacuum has been secured from the upstream side of Zone 2 CM in the vault

10/24/2017 - 480 VAC panels are being mounted in gallery

10/11/2017 - Waveguide design review

10/10/2017 - Clean Hoods have been moved to vault

10/9/2017 - Electricians have "Air Gapped" all power connections to FL03 & FL04 CPS & HPAs