+ | Remaining tasks for LCLS-II Cryomodule testing | ||
+ | Kevin Jordan 7/26/2018 | ||
+ | System Task Group Responsible Notes | ||
+ | Installation / Pipe fitting / Welding PRIOR to testing | ||
+ | Transferline | ||
+ | Confirm/Prep both transferline sections have proper weld prep Cryo | ||
+ | Locate and affix to floor short piece Installation | ||
+ | Locate and affix to floor "L" piece Installation | ||
+ | Position/align both sections with ruler and level bar Cryo | ||
+ | Cut, prep, & weld field fit joints per weld spec - w/M. Martin advice Cryo | ||
+ | Leak check innner connections prior to SI wrap Cryo/SRF? | ||
+ | Cut/prep & weld clam shells Cryo | ||
+ | |||
+ | Warm Helium Piping | ||
+ | Prep, mount, and weld sections of warm piping per spec & drawings Cryo Much of this is to be done after the cryo-can is located & grouted | ||
+ | |||
+ | Cryo-Can | ||
+ | Remove/install equipment that is too tall for cable tray/waveguide Gubeli Ensure that it can be moved into place w/o hight restrictions like relief stack | ||
+ | Confirm/Prep the weld joints have proper weld prep Cryo | ||
+ | Locate Cryo-can per surveyed drill locations Installation | ||
+ | Confirm alignment to field fit transferline Survey/Gubeli | ||
+ | Drill, mount/level can, grout base plate Installation | ||
+ | Cut to fit, weld & leak check inner Helium piping Cryo | ||
+ | Wrap SI insulation Cryo/SRF | ||
+ | Cut to fit & weld outer clam shells Cryo | ||
+ | |||
+ | Clean Room Assembly | ||
+ | Unpack & assemble Electricians This can be done once the cryo-Can has been moved into place | ||
+ | Install AC power and lights Electricians | ||
+ | |||
+ | |||
+ | |||
+ | |||
+ | |||
+ | |||
− | == | + | === Work to move, locate, and join 2 cryomodules prior to testing === |
− | + | ||
− | |||
− | |||
− | == Cryo-Can | + | == Movement == |
− | * | + | |
− | + | Bolt on wheels SRF Installation crew can assist if required | |
− | + | Arrange for crane at LERF to Lower/Raise CMs Installation | |
− | + | Move to/from Test Lab SRF | |
− | + | Wheel in/out LERF SFR/Installation | |
− | + | Locate/position CMs SFR/Survey This will likely be done wioth plumb bobs | |
− | + | ||
− | + | Cleanroom beam tube connection | |
− | + | Prepare & execute center beam tube connections in cleam room per procedures SRF/Vac This is the effort to join two modules together | |
+ | Insulate SRF | ||
+ | |||
+ | Cryo-Can & Center Bellows * these details are TBD * | ||
+ | Affix the bellows to cart Installation (?) The cryo-can bellows may arrive on the end of the CM - TBD | ||
+ | Position cryo-can bellows SRF The cart enables ease of installation in the joining region | ||
+ | Secure cryo-can bellows SRF | ||
+ | Position center bellows These connect the vacuum space of the two CMs together | ||
+ | Secure center bellows | ||
+ | |||
+ | Cooldown | ||
+ | Follow Mike Drury's proceedures |
Revision as of 09:35, 27 July 2018
Remaining tasks for LCLS-II Cryomodule testing Kevin Jordan 7/26/2018 System Task Group Responsible Notes Installation / Pipe fitting / Welding PRIOR to testing Transferline Confirm/Prep both transferline sections have proper weld prep Cryo Locate and affix to floor short piece Installation Locate and affix to floor "L" piece Installation Position/align both sections with ruler and level bar Cryo Cut, prep, & weld field fit joints per weld spec - w/M. Martin advice Cryo Leak check innner connections prior to SI wrap Cryo/SRF? Cut/prep & weld clam shells Cryo
Warm Helium Piping Prep, mount, and weld sections of warm piping per spec & drawings Cryo Much of this is to be done after the cryo-can is located & grouted
Cryo-Can Remove/install equipment that is too tall for cable tray/waveguide Gubeli Ensure that it can be moved into place w/o hight restrictions like relief stack Confirm/Prep the weld joints have proper weld prep Cryo Locate Cryo-can per surveyed drill locations Installation Confirm alignment to field fit transferline Survey/Gubeli Drill, mount/level can, grout base plate Installation Cut to fit, weld & leak check inner Helium piping Cryo Wrap SI insulation Cryo/SRF Cut to fit & weld outer clam shells Cryo
Clean Room Assembly Unpack & assemble Electricians This can be done once the cryo-Can has been moved into place Install AC power and lights Electricians
Work to move, locate, and join 2 cryomodules prior to testing
Movement
Bolt on wheels SRF Installation crew can assist if required Arrange for crane at LERF to Lower/Raise CMs Installation Move to/from Test Lab SRF Wheel in/out LERF SFR/Installation Locate/position CMs SFR/Survey This will likely be done wioth plumb bobs
Cleanroom beam tube connection Prepare & execute center beam tube connections in cleam room per procedures SRF/Vac This is the effort to join two modules together Insulate SRF
Cryo-Can & Center Bellows * these details are TBD * Affix the bellows to cart Installation (?) The cryo-can bellows may arrive on the end of the CM - TBD Position cryo-can bellows SRF The cart enables ease of installation in the joining region Secure cryo-can bellows SRF Position center bellows These connect the vacuum space of the two CMs together Secure center bellows
Cooldown Follow Mike Drury's proceedures