Difference between revisions of "Upcoming Activities"

From LCLS-II testing
Jump to navigation Jump to search
(Created page with "* Remove waveguide in tunnel from zone 3 and 4 * Finish ceiling layout for waveguide supports * Start hanging waveguide in the tunnel * Get AC power to racks in gallery * Inst...")
 
Line 3: Line 3:
 
* Start hanging waveguide in the tunnel
 
* Start hanging waveguide in the tunnel
 
* Get AC power to racks in gallery
 
* Get AC power to racks in gallery
 +
* Hang tray over new racks (NOT above SSAs)
 
* Install servers & UPS
 
* Install servers & UPS
 
* Move (crane) SSAs to gallery - when will #16 arrive?
 
* Move (crane) SSAs to gallery - when will #16 arrive?
 +
* Finalize design & procure false floor parts
 +
* Pull cable...
 +
* Terminate cable...
 +
 +
Cryo racks will be here in March
 +
 +
LLRF Racks arrive in ???
 +
 +
Magnet power supply racks arrive in ???

Revision as of 11:43, 24 January 2018

  • Remove waveguide in tunnel from zone 3 and 4
  • Finish ceiling layout for waveguide supports
  • Start hanging waveguide in the tunnel
  • Get AC power to racks in gallery
  • Hang tray over new racks (NOT above SSAs)
  • Install servers & UPS
  • Move (crane) SSAs to gallery - when will #16 arrive?
  • Finalize design & procure false floor parts
  • Pull cable...
  • Terminate cable...

Cryo racks will be here in March

LLRF Racks arrive in ???

Magnet power supply racks arrive in ???