Difference between revisions of "Upcoming Activities"

From LCLS-II testing
Jump to navigation Jump to search
Line 1: Line 1:
* Remove waveguide in tunnel from zone 3 and 4
+
* Remove waveguide in tunnel from zone 3 and 4 - DONE
* Finish ceiling layout for waveguide supports
+
* Finish ceiling layout for waveguide supports - DONE
 
* Start hanging waveguide in the tunnel
 
* Start hanging waveguide in the tunnel
 
* Get AC power to racks in gallery
 
* Get AC power to racks in gallery
 
* Hang tray over new racks (NOT above SSAs)
 
* Hang tray over new racks (NOT above SSAs)
 
* Install servers & UPS
 
* Install servers & UPS
* Move (crane) SSAs to gallery - when will #16 arrive?
+
* Move (crane) SSAs to gallery - when will #16 arrive? (March)
 
* Finalize design & procure false floor parts
 
* Finalize design & procure false floor parts
 
* Pull cable...
 
* Pull cable...
Line 12: Line 12:
 
Cryo racks will be here in March
 
Cryo racks will be here in March
  
LLRF Racks arrive in ???
+
LLRF Racks arrive in early April
  
 
Magnet power supply racks arrive in ???
 
Magnet power supply racks arrive in ???

Revision as of 11:34, 31 January 2018

  • Remove waveguide in tunnel from zone 3 and 4 - DONE
  • Finish ceiling layout for waveguide supports - DONE
  • Start hanging waveguide in the tunnel
  • Get AC power to racks in gallery
  • Hang tray over new racks (NOT above SSAs)
  • Install servers & UPS
  • Move (crane) SSAs to gallery - when will #16 arrive? (March)
  • Finalize design & procure false floor parts
  • Pull cable...
  • Terminate cable...

Cryo racks will be here in March

LLRF Racks arrive in early April

Magnet power supply racks arrive in ???