Line 5: | Line 5: | ||
* Start hanging waveguide in the tunnel | * Start hanging waveguide in the tunnel | ||
* Get AC power to racks in gallery | * Get AC power to racks in gallery | ||
− | * Hang tray over new racks | + | * Hang tray over new racks |
* Install servers & UPS | * Install servers & UPS | ||
* Move (crane) SSAs to gallery - when will #16 arrive? (March) | * Move (crane) SSAs to gallery - when will #16 arrive? (March) |
Revision as of 12:20, 6 February 2018
Design water manifold for SSAs & Isolators
- Remove waveguide in tunnel from zone 3 and 4 - DONE
- Finish ceiling layout for waveguide supports - DONE
- Start hanging waveguide in the tunnel
- Get AC power to racks in gallery
- Hang tray over new racks
- Install servers & UPS
- Move (crane) SSAs to gallery - when will #16 arrive? (March)
- Finalize design & procure false floor parts
- Pull cable...
- Terminate cable...
Cryo racks will be here in March
LLRF Racks arrive in early April
Magnet power supply racks arrive in ???