* Remove waveguide in tunnel from zone 3 and 4
+
[[Installation and welding activities]]
* Finish ceiling layout for waveguide supports
+
 
* Start hanging waveguide in the tunnel
+
* Complete PSS connections
* Get AC power to racks in gallery
+
* Turn on control power to SSAs
* Install servers & UPS
+
* Finish CM # 1 tunnel waveguide
* Move (crane) SSAs to gallery - when will #16 arrive?
+
* Start pulling and terminating cables
 +
* Get Cryo-cons installed and operational
 +
* Design water manifold for SSAs & Isolators
 +
* Remove waveguide in tunnel from zone 3 and 4 - DONE
 +
* Finish ceiling layout for waveguide supports - DONE
 +
* Start hanging waveguide in the tunnel - STARTED
 +
* Get AC power to racks in gallery - STARTED
 +
* Hang tray over new racks - STARTED
 +
* Install servers & UPS - DONE
 +
* Move (crane) SSAs to gallery - DONE - when will #16 arrive? (March)
 +
* Finalize design & procure false floor parts
 +
* Pull cable...
 +
* Terminate cable...
 +
 
 +
Cryo racks will be here in March
 +
 
 +
LLRF Racks arrive in early April
 +
 
 +
Magnet power supply racks arrive in ???

Latest revision as of 13:49, 19 July 2018

Installation and welding activities

  • Complete PSS connections
  • Turn on control power to SSAs
  • Finish CM # 1 tunnel waveguide
  • Start pulling and terminating cables
  • Get Cryo-cons installed and operational
  • Design water manifold for SSAs & Isolators
  • Remove waveguide in tunnel from zone 3 and 4 - DONE
  • Finish ceiling layout for waveguide supports - DONE
  • Start hanging waveguide in the tunnel - STARTED
  • Get AC power to racks in gallery - STARTED
  • Hang tray over new racks - STARTED
  • Install servers & UPS - DONE
  • Move (crane) SSAs to gallery - DONE - when will #16 arrive? (March)
  • Finalize design & procure false floor parts
  • Pull cable...
  • Terminate cable...

Cryo racks will be here in March

LLRF Racks arrive in early April

Magnet power supply racks arrive in ???