Difference between revisions of "Upcoming Activities"
Jump to navigation
Jump to search
(2 intermediate revisions by the same user not shown) | |||
Line 1: | Line 1: | ||
− | + | [[Installation and welding activities]] | |
+ | * Complete PSS connections | ||
+ | * Turn on control power to SSAs | ||
+ | * Finish CM # 1 tunnel waveguide | ||
+ | * Start pulling and terminating cables | ||
+ | * Get Cryo-cons installed and operational | ||
+ | * Design water manifold for SSAs & Isolators | ||
* Remove waveguide in tunnel from zone 3 and 4 - DONE | * Remove waveguide in tunnel from zone 3 and 4 - DONE | ||
* Finish ceiling layout for waveguide supports - DONE | * Finish ceiling layout for waveguide supports - DONE | ||
− | * Start hanging waveguide in the tunnel | + | * Start hanging waveguide in the tunnel - STARTED |
− | * Get AC power to racks in gallery | + | * Get AC power to racks in gallery - STARTED |
− | * Hang tray over new racks | + | * Hang tray over new racks - STARTED |
− | * Install servers & UPS | + | * Install servers & UPS - DONE |
− | * Move (crane) SSAs to gallery - when will #16 arrive? (March) | + | * Move (crane) SSAs to gallery - DONE - when will #16 arrive? (March) |
* Finalize design & procure false floor parts | * Finalize design & procure false floor parts | ||
* Pull cable... | * Pull cable... |
Latest revision as of 13:49, 19 July 2018
Installation and welding activities
- Complete PSS connections
- Turn on control power to SSAs
- Finish CM # 1 tunnel waveguide
- Start pulling and terminating cables
- Get Cryo-cons installed and operational
- Design water manifold for SSAs & Isolators
- Remove waveguide in tunnel from zone 3 and 4 - DONE
- Finish ceiling layout for waveguide supports - DONE
- Start hanging waveguide in the tunnel - STARTED
- Get AC power to racks in gallery - STARTED
- Hang tray over new racks - STARTED
- Install servers & UPS - DONE
- Move (crane) SSAs to gallery - DONE - when will #16 arrive? (March)
- Finalize design & procure false floor parts
- Pull cable...
- Terminate cable...
Cryo racks will be here in March
LLRF Racks arrive in early April
Magnet power supply racks arrive in ???