Difference between revisions of "Upcoming Activities"

From LCLS-II testing
Jump to navigation Jump to search
Line 1: Line 1:
 +
* Complete PSS connections
 +
* Turn on control power to SSAs
 +
* Finish CM # 1 tunnel waveguide
 +
* Start pulling and terminating cables
 +
* Get Cryo-cons installed and operational
 
* Design water manifold for SSAs & Isolators
 
* Design water manifold for SSAs & Isolators
 
* Remove waveguide in tunnel from zone 3 and 4 - DONE
 
* Remove waveguide in tunnel from zone 3 and 4 - DONE

Revision as of 08:31, 27 February 2018

  • Complete PSS connections
  • Turn on control power to SSAs
  • Finish CM # 1 tunnel waveguide
  • Start pulling and terminating cables
  • Get Cryo-cons installed and operational
  • Design water manifold for SSAs & Isolators
  • Remove waveguide in tunnel from zone 3 and 4 - DONE
  • Finish ceiling layout for waveguide supports - DONE
  • Start hanging waveguide in the tunnel - STARTED
  • Get AC power to racks in gallery - STARTED
  • Hang tray over new racks - STARTED
  • Install servers & UPS - DONE
  • Move (crane) SSAs to gallery - DONE - when will #16 arrive? (March)
  • Finalize design & procure false floor parts
  • Pull cable...
  • Terminate cable...

Cryo racks will be here in March

LLRF Racks arrive in early April

Magnet power supply racks arrive in ???