Upcoming Activities

From LCLS-II testing
Revision as of 11:34, 31 January 2018 by Jordan (talk | contribs)
Jump to navigation Jump to search
  • Remove waveguide in tunnel from zone 3 and 4 - DONE
  • Finish ceiling layout for waveguide supports - DONE
  • Start hanging waveguide in the tunnel
  • Get AC power to racks in gallery
  • Hang tray over new racks (NOT above SSAs)
  • Install servers & UPS
  • Move (crane) SSAs to gallery - when will #16 arrive? (March)
  • Finalize design & procure false floor parts
  • Pull cable...
  • Terminate cable...

Cryo racks will be here in March

LLRF Racks arrive in early April

Magnet power supply racks arrive in ???