GTS meeting 7 29 19
Jump to navigation
Jump to search
- Survey:
- Overview:
- HV Processing needs to be done
- Survey and alignment was completed. Final placement of solenoid needs to be set
- SMA cable causing RF issue has been replaced and final RF work needs to be done
- DC Bias Supply is in John Musson's Lab being modified and tested: working schedule unknown
- open valve to beam-line and produce initial beam
- determine cut-off voltages with solenoid on/off
- produce RF bunched beam of specific bunch charges
- measure bunch properties of magnetized and non-magnetized beam
- produce 65 mA magnetized beam as part of Xelera deliverables
- 7/29 work plan:
- complete gun enclosure for corona mitigating nitrogen flow
- Install radiation monitors
- modify Hot deck HV contact
- finalize Solenoid placement
- connect the anode bias
- 7/30 work plan:
- set up camera to visually monitor HV (waiting on updated software)
- Standard HV processing
- HV processing with solenoid on if standard HVP goes well
- 7/31 work plan:
- Finish RF work, Final check of SCAM and create supply to voltage chart
- Check DC Bias Supply progress (possibly reinstall)
- 8/1-onward work plan:
- Depends on what happens up to this date...