July 11,, 2019 - Weekly AIPINJ Meeting
Jump to navigation
Jump to search
Agenda
- Schedule
- Whiteboard pic media:190711_down.jpg
- Suggests installation & commissioning plan like this:
- May-Oct ~ 6 months to rebuild the 200keV beam line (gun, chopper, up to QCM)
- Nov ~ Booster/QCM swap between CEBAF/UITF
- Dec-Jan ~ Install and instrument Booster at CEBAF, cool and SRF testing
- Feb-Mar ~ Commissiong 10 MeV beam to FC2, ILD?
- Layout/Tasks
- Simulations
- elegant layout gun to QCM by ~ end of July
- gpt ~ goals are?