MOLLER PQB Meeting October 2, 2024

From Ciswikidb
Jump to navigation Jump to search

In person in MCC Conference Room and with Zoom.

https://wiki.jlab.org/ciswiki/index.php/Parity_Quality_Beam

--


Agenda:


  • Injector Upgrade Progress:
  1. RTP new HV Driver full system is finally ready:
    1. Burn-in at 30 Hz started last week
    2. Installation Schedule: media:RTP_Installation_Schedule.pdf


  • MOLLER new rack in ISB - IN03B25 - will be powered up on 10/3/2025, equipped with UPS: media:IMG_1910.jpg