Meeting 3/31/22 - COMTRA
Jump to navigation
Jump to search
Agenda
- Eric's plan at IJCLab for crystals
- Hall A detectors NaI(Tl?) media:220331_HallA_NaI2.jpg
- IJCLab xstal - winner!
- Saint Gobain xstal - long lead (backups?)
- Alpha spectra xstal - inclusions
- Berkeley Nucleonics - no reply
- DAQ status
- Magnet status
- Steel inventory media:220324_Steel.jpg
- Steel report media:Compton_East Carolina Metal treatment metallurgy_3_24_2022.pdf
- Sandesh preliminary media:UPDATE 1 -COMPTON POLARIZED TARGET MAXWELL Field analysis 032522.pptx
- UITF plan
- April - finish design & assembly of Wien and Mott hardware, finish 200 KV HV vac work,
- May - install Wien/Mott UITF, finish 200 KV gun assembly, restore polarized laser UITF
- June - install 200 keV gun, bake, big job, goal is making beam by ~July 4th weekend
- July - make 200 keV polarized beam, calibrate the Mott, using ~nA beam and U-Wien
- Aug - install Compton in MeV section, run keV beam as needed
- Sep/Oct - calibrate Compton, two separate ~week long runs
- Wien/Mott layouts