Agenda
1. Proposed Installation Schedule Winter SAD Schedule
- There are ~3 weeks in January for this job: Jan 3 (return to work) to Jan 27 (CEBAF restoration)
- Week 1 (Jan 4-11) Install LLRF, connect lasers when makes sense, test ability to move between 250/500, verify proper power levels to lasers, and check reproducibility.
- Week 2 (Jan 12-18) Injector lock-ups and make e-beam, test against rf sensitive elements like bunchers, chopper, and unit when 2K is restored.
- Week 3 (Jan 19-25) Evaluate and make sure front end is performing well, finalize/rectify outstanding issues, worst case backout.
2. Tomasz - LLRF update
3. Software Request to switch laser/LLRF between 250/499 MHz media:161012_4Laser4LLRF.docx