Difference between revisions of "MOLLER PQB Meeting September 4, 2024"
Jump to navigation
Jump to search
Line 15: | Line 15: | ||
# Gun was conditioned to 200 kV without field emission | # Gun was conditioned to 200 kV without field emission | ||
− | # Beam tests showed excellent beam quality and good transmission at 100 | + | # Beam tests showed excellent beam quality and good transmission at 100 μA: [[media:R30-4_gun_beam_comm.pdf]] [[media:R30-4_gun_beam_comm.pptx]] |
# RTP new HV Driver full system testing started this week | # RTP new HV Driver full system testing started this week | ||
Latest revision as of 13:33, 11 September 2024
In person in MCC Conference Room and with Zoom.
https://wiki.jlab.org/ciswiki/index.php/Parity_Quality_Beam
--
Agenda:
- Reminder: Accelerator MOLLER Project Meeting is on Monday September 9th, 3-4 pm
- Injector Upgrade Progress:
- Gun was conditioned to 200 kV without field emission
- Beam tests showed excellent beam quality and good transmission at 100 μA: media:R30-4_gun_beam_comm.pdf media:R30-4_gun_beam_comm.pptx
- RTP new HV Driver full system testing started this week
- Beam Study Results:
- FFB/FF in Hall A:
- May beam test, FFT and width, Xiang Zhang: media:2024May_FFBtest_Results.pdf
- Check FFB ON versus OFF in QWeak data
- 2010 QWeak Data: [1]