Notes from this meeting:
 
Notes from this meeting:
  
 +
* Radiator:
 
  - The power deposited in the radiator for 200 uA and 8.5 MeV electron beam:
 
  - The power deposited in the radiator for 200 uA and 8.5 MeV electron beam:
 
   For 0.02 mm radiator, average energy loss is about 24 keV, P = 4.8 W
 
   For 0.02 mm radiator, average energy loss is about 24 keV, P = 4.8 W
Line 34: Line 35:
 
   Re-evaluate radiator cooling  
 
   Re-evaluate radiator cooling  
 
   What is the temperature of the LCW that will be used to cool the radiator?
 
   What is the temperature of the LCW that will be used to cool the radiator?
 +
- On the radiator ladder, we should have a viewer and preferable a YAG viewer to check the beam size
 +
- Need a camera to look at the OTR light coming from the radiator
  
  - Need a HARP in the new Bubble Chamber line to measure the size of the beam impinging on the radiator
+
  - Need a layout of the beam line. What is the location of the radiator on the beam line?
  - On the radiator ladder, we should have a viewer and preferable a YAG viewer to check the beam size
+
  - Need a HARP in the new Bubble Chamber line to measure beam profile and energy spread
  - Need a camera to look at the OTR coming from the radiator
+
  - Where to put the electron dump (2-ft cube footprint)? Injector floor or on the Step.
 
  - What is the clearance between the wall and the Laser Room in the Injector?
 
  - What is the clearance between the wall and the Laser Room in the Injector?
 
  - Safety:
 
  - Safety:

Revision as of 09:38, 1 August 2013

We will meet in TED 2561B on Wednesday July 24 at 3:00 pm EST.

For those calling in we'll use the ReadyTalk audio conference system.

1. Dial Toll-Free Number: 866-740-1260 (U.S. & Canada)
2. Enter 7-digit access code 4402297, followed by “#”

Agenda:

 media:Meeting_24July_2013.pdf
 media:Meeting_24July_2013.pptx  

1- Schedule

2- Design of beamline, radiator and dump

  • Experiment beam line today is presently decommissioned, ready for modification:
5D beam line

3- Bubble Chamber work at Argonne

4- Background and simulation

5- Absolute beam energy

6- Safety



Notes from this meeting:

  • Radiator:
- The power deposited in the radiator for 200 uA and 8.5 MeV electron beam:
  For 0.02 mm radiator, average energy loss is about 24 keV, P = 4.8 W
  For 0.10 mm radiator, average energy loss is about 120 keV, P = 24 W
  Re-evaluate radiator cooling 
  What is the temperature of the LCW that will be used to cool the radiator?
- On the radiator ladder, we should have a viewer and preferable a YAG viewer to check the beam size
- Need a camera to look at the OTR light coming from the radiator
- Need a layout of the beam line. What is the location of the radiator on the beam line?
- Need a HARP in the new Bubble Chamber line to measure beam profile and energy spread
- Where to put the electron dump (2-ft cube footprint)? Injector floor or on the Step.
- What is the clearance between the wall and the Laser Room in the Injector?
- Safety:
  The sweep dipole must be in FSD to protect the exit window
  There will be about 500 ml of mercury used a buffer liquid in the chamber
- We will meet every two weeks on Wednesdays at 3:00 to 5:00 EST