Difference between revisions of "Bubble Chamber Meeting Wednesday July 1, 2015"
Jump to navigation
Jump to search
(6 intermediate revisions by the same user not shown) | |||
Line 23: | Line 23: | ||
# Made the 27" stand for JLab Injector beamline | # Made the 27" stand for JLab Injector beamline | ||
# Ready to start crating, expect to ship by mid-July | # Ready to start crating, expect to ship by mid-July | ||
− | # Upon arrival at JLab, move to Injector tunnel | + | # Cannot yet ship N<sub>2</sub>O – needs JLab and Argonne approval |
+ | # Upon arrival at JLab at the end of July, move to Injector tunnel | ||
# Brad will provide description of the shipment and handling instruction | # Brad will provide description of the shipment and handling instruction | ||
# Brad will be at JLab August 3 – 12. | # Brad will be at JLab August 3 – 12. | ||
Line 31: | Line 32: | ||
# Started pressure system approval process | # Started pressure system approval process | ||
# Will need Electrical Review since we have 208 V custom-made electrical distribution box | # Will need Electrical Review since we have 208 V custom-made electrical distribution box | ||
− | # Need a TOSP with all the operational and safety procedures (fire, ...) | + | # Need a TOSP with all the operational and safety procedures (fire, power loss, ...) |
# List of fluids: | # List of fluids: | ||
## Mercury: 150 mL | ## Mercury: 150 mL | ||
Line 40: | Line 41: | ||
* Cancelled shifts of beam scheduled for August except for swing shifts in second week | * Cancelled shifts of beam scheduled for August except for swing shifts in second week | ||
+ | |||
+ | |||
+ | * Bubble Chamber Installation: Tasks and Schedule – Summer 2015: [[media:Bubble_Install_Summer15.pdf]] [[media:Bubble_Install_Summer15.pptx]] | ||
+ | # Dan Moser is our OPS liaison | ||
+ | # Accelerator schedule after August 15 is being reworked. |
Latest revision as of 08:50, 8 July 2015
We will meet in TL 2221 on Wednesday July 1 at 3:30 pm EST.
For those calling in we'll use the Blue Jeans [1] audio conference system.
Phone number: 1-888-240-2560 Meeting ID: 3528502673# Meeting URL: http://bluejeans.com/3528502673
Agenda:
1- Bubble Chamber progress at Argonne
Notes from this meeting:
- Bubble Chamber:
- Made the 27" stand for JLab Injector beamline
- Ready to start crating, expect to ship by mid-July
- Cannot yet ship N2O – needs JLab and Argonne approval
- Upon arrival at JLab at the end of July, move to Injector tunnel
- Brad will provide description of the shipment and handling instruction
- Brad will be at JLab August 3 – 12.
- Safety Reviews:
- Started pressure system approval process
- Will need Electrical Review since we have 208 V custom-made electrical distribution box
- Need a TOSP with all the operational and safety procedures (fire, power loss, ...)
- List of fluids:
- Mercury: 150 mL
- Superheated Liquid (N2O or C2F6): 40 – 60 mL
- Hydraulic Fluid: 5 gal
- Silicone Oil for Chiller: 2 L
- Cancelled shifts of beam scheduled for August except for swing shifts in second week
- Bubble Chamber Installation: Tasks and Schedule – Summer 2015: media:Bubble_Install_Summer15.pdf media:Bubble_Install_Summer15.pptx
- Dan Moser is our OPS liaison
- Accelerator schedule after August 15 is being reworked.