+ | === Summer 2017 SAD Update === | ||
+ | :[[media:SADCIS_v6.docx]] | ||
+ | |||
===200kV Gun=== | ===200kV Gun=== | ||
* Task and Timeline Gantt chart => [[media:170421_CHG.pdf]] | * Task and Timeline Gantt chart => [[media:170421_CHG.pdf]] | ||
+ | :Simulation of the effect of the mesh and the perforated plate [[media:170525_Mesh.pdf]] | ||
− | === | + | === NEG Tube=== |
− | |||
− | |||
− | |||
: We are making 4 BPM's | : We are making 4 BPM's | ||
: Shop has materials now and machining (#327755) | : Shop has materials now and machining (#327755) | ||
− | : Phil will pick up for weld, 400C bake, leak check, clean, NEG coat | + | : ...then Phil will pick up for weld, 400C bake, leak check, clean, NEG coat |
− | : Pete will perform optical/electrical checks | + | : ...then Pete will perform optical/electrical checks |
− | : John will perform Gabou map | + | : ...then John will perform Gabou map |
::Final NEG tube design => [[media:NEGTUBE_MAY03.pdf]] | ::Final NEG tube design => [[media:NEGTUBE_MAY03.pdf]] | ||
::M20 Old Assembly Modification [[media:0990.pdf]] | ::M20 Old Assembly Modification [[media:0990.pdf]] | ||
Line 16: | Line 17: | ||
::M20 New Assembly 6.00 x 4.500 reducer flange[[media:0.992.pdf]] | ::M20 New Assembly 6.00 x 4.500 reducer flange[[media:0.992.pdf]] | ||
− | === | + | ===Diagnostics Chamber Installation === |
: Second bake and activate week of May 30th => [http://opsweb.acc.jlab.org/CSUEApps/atlis/task/17278 Remove and replace Gun3 ATLIS task] | : Second bake and activate week of May 30th => [http://opsweb.acc.jlab.org/CSUEApps/atlis/task/17278 Remove and replace Gun3 ATLIS task] | ||
: Remove VBV3I02 from special interlock and swap PLC for relays | : Remove VBV3I02 from special interlock and swap PLC for relays | ||
− | ===Spellman HVPS | + | ===TOSP/Spellman HVPS update=== |
− | + | :UITF [[media:UITF-TOSP.pdf]] [[media:UITF-THA.pdf]] | |
− | |||
− | :[ | ||
− | |||
− | |||
− | |||
− |
Latest revision as of 10:05, 26 May 2017
Summer 2017 SAD Update
200kV Gun
- Task and Timeline Gantt chart => media:170421_CHG.pdf
- Simulation of the effect of the mesh and the perforated plate media:170525_Mesh.pdf
NEG Tube
- We are making 4 BPM's
- Shop has materials now and machining (#327755)
- ...then Phil will pick up for weld, 400C bake, leak check, clean, NEG coat
- ...then Pete will perform optical/electrical checks
- ...then John will perform Gabou map
- Final NEG tube design => media:NEGTUBE_MAY03.pdf
- M20 Old Assembly Modification media:0990.pdf
- M20 New Assembly Can media:0991.pdf
- M20 New Assembly 6.00 x 4.500 reducer flangemedia:0.992.pdf
Diagnostics Chamber Installation
- Second bake and activate week of May 30th => Remove and replace Gun3 ATLIS task
- Remove VBV3I02 from special interlock and swap PLC for relays