Difference between revisions of "November 20, 2013"
Jump to navigation
Jump to search
(Created page with "=== Mott Team Meeting === We will meet next on Wednesday November 20th at 3pm EST locally in TL-1227 (1st floor conference room near CIS offices) or call in by ReadyTalk details...") |
|||
(8 intermediate revisions by the same user not shown) | |||
Line 7: | Line 7: | ||
2. Enter 7-digit access code 3441852, followed by “#” | 2. Enter 7-digit access code 3441852, followed by “#” | ||
− | = | + | = Commissioning = |
− | ; | + | ; Schedule Update |
− | + | * Dec 2 - Dec 16 : injector commissioning (parasitic opportunity) | |
+ | * Dec 7 : mott commissioning 0400 - 2000 (will ask to break into 4+12) | ||
+ | * Jan (2-10) - Feb 6 : 1-pass commissioning (parasitic opportunity) | ||
+ | * Feb 6 - Feb 27 : SAD (vent for dump, fix mirror, ideally new targets) | ||
+ | * Feb 28 - June 6 : ACC-II (long commissioning run) | ||
− | |||
− | |||
; Target ladder | ; Target ladder | ||
+ | * Update [[Media:131120_MottLadder.pdf]] | ||
+ | |||
; Reduced rep rate beam | ; Reduced rep rate beam | ||
+ | * Update [[Media:131120_SeedPulsing.pdf]] | ||
+ | |||
; DAQ status | ; DAQ status | ||
+ | |||
+ | = New Dump = | ||
+ | ; Status | ||
+ | * Given present schedule want parts in-hand by Jan 17th | ||
+ | * Be plate - Materion sending quote, will turn into PR | ||
+ | * Cu end cap - RFQ's sent to 3 local vendors today | ||
+ | * Cu cooling - once vendor is building part, will fab LCW circuit | ||
+ | * New dump will go in; thermal analysis will speak to max current | ||
+ | |||
+ | ; Simulations |
Latest revision as of 10:16, 20 November 2013
Mott Team Meeting
We will meet next on Wednesday November 20th at 3pm EST locally in TL-1227 (1st floor conference room near CIS offices) or call in by ReadyTalk details below.
For those calling in we'll use the ReadyTalk audio conference system.
1. Dial Toll-Free Number: 866-740-1260 (U.S. & Canada) 2. Enter 7-digit access code 3441852, followed by “#”
Commissioning
- Schedule Update
- Dec 2 - Dec 16 : injector commissioning (parasitic opportunity)
- Dec 7 : mott commissioning 0400 - 2000 (will ask to break into 4+12)
- Jan (2-10) - Feb 6 : 1-pass commissioning (parasitic opportunity)
- Feb 6 - Feb 27 : SAD (vent for dump, fix mirror, ideally new targets)
- Feb 28 - June 6 : ACC-II (long commissioning run)
- Target ladder
- Update Media:131120_MottLadder.pdf
- Reduced rep rate beam
- Update Media:131120_SeedPulsing.pdf
- DAQ status
New Dump
- Status
- Given present schedule want parts in-hand by Jan 17th
- Be plate - Materion sending quote, will turn into PR
- Cu end cap - RFQ's sent to 3 local vendors today
- Cu cooling - once vendor is building part, will fab LCW circuit
- New dump will go in; thermal analysis will speak to max current
- Simulations