Difference between revisions of "GTS meeting 7 29 19"
Jump to navigation
Jump to search
(One intermediate revision by one other user not shown) | |||
Line 2: | Line 2: | ||
:: [[media:DT_F1933.pdf]] | :: [[media:DT_F1933.pdf]] | ||
:: Drawing: [[media:TGun_Cathode_drawing.pdf]] | :: Drawing: [[media:TGun_Cathode_drawing.pdf]] | ||
− | :: | + | |
− | :: | + | * Overview: |
+ | ** HV Processing needs to be done | ||
+ | ** Survey and alignment was completed. Final placement of solenoid needs to be set | ||
+ | ** SMA cable causing RF issue has been replaced and final RF work needs to be done | ||
+ | ** DC Bias Supply is in John Musson's Lab being modified and tested: working schedule unknown | ||
+ | ** open valve to beam-line and produce initial beam | ||
+ | ** determine cut-off voltages with solenoid on/off | ||
+ | ** produce RF bunched beam of specific bunch charges | ||
+ | ** measure bunch properties of magnetized and non-magnetized beam | ||
+ | ** produce 65 mA magnetized beam as part of Xelera deliverables | ||
+ | |||
+ | |||
+ | * 7/29 work plan: | ||
+ | ** complete gun enclosure for corona mitigating nitrogen flow | ||
+ | ** Install radiation monitors | ||
+ | ** modify Hot deck HV contact | ||
+ | ** finalize Solenoid placement | ||
+ | ** connect the anode bias | ||
+ | |||
+ | * 7/30 work plan: | ||
+ | ** set up camera to visually monitor HV (waiting on updated software) | ||
+ | ** Standard HV processing | ||
+ | ** HV processing with solenoid on if standard HVP goes well | ||
+ | |||
+ | * 7/31 work plan: | ||
+ | ** Finish RF work, Final check of SCAM and create supply to voltage chart | ||
+ | ** Check DC Bias Supply progress (possibly reinstall) | ||
+ | |||
+ | * 8/1-onward work plan: | ||
+ | ** Depends on what happens up to this date... |
Latest revision as of 08:45, 29 July 2019
- Survey:
- Overview:
- HV Processing needs to be done
- Survey and alignment was completed. Final placement of solenoid needs to be set
- SMA cable causing RF issue has been replaced and final RF work needs to be done
- DC Bias Supply is in John Musson's Lab being modified and tested: working schedule unknown
- open valve to beam-line and produce initial beam
- determine cut-off voltages with solenoid on/off
- produce RF bunched beam of specific bunch charges
- measure bunch properties of magnetized and non-magnetized beam
- produce 65 mA magnetized beam as part of Xelera deliverables
- 7/29 work plan:
- complete gun enclosure for corona mitigating nitrogen flow
- Install radiation monitors
- modify Hot deck HV contact
- finalize Solenoid placement
- connect the anode bias
- 7/30 work plan:
- set up camera to visually monitor HV (waiting on updated software)
- Standard HV processing
- HV processing with solenoid on if standard HVP goes well
- 7/31 work plan:
- Finish RF work, Final check of SCAM and create supply to voltage chart
- Check DC Bias Supply progress (possibly reinstall)
- 8/1-onward work plan:
- Depends on what happens up to this date...