Difference between revisions of "200 kV Polarized Gun"

From Ciswikidb
Jump to navigation Jump to search
 
(26 intermediate revisions by 2 users not shown)
Line 3: Line 3:
 
* This gun performed as designed in terms of vacuum, and high voltage: no field emission at 200 kV after conditioning with Kr to ~240 kV.
 
* This gun performed as designed in terms of vacuum, and high voltage: no field emission at 200 kV after conditioning with Kr to ~240 kV.
 
* It has two problems:
 
* It has two problems:
* a) The beam waist is ~ 6 cm downstream of the GaAs wafer, compared to ~ 40 cm from the Tee electrode 14" HVC R28-2 gun operated in CEBAF for years at 130 kV.
+
** The beam waist is ~ 6 cm downstream of the GaAs wafer, compared to ~ 40 cm from the Tee electrode 14" HVC R28-2 gun operated in CEBAF for years at 130 kV.
* b) It was a not possible to obtain the laser retro-reflection.
+
** It was a not possible to obtain the laser retro-reflection.
 
* The gun was then removed from the injector and replaced with the R28-2 gun.
 
* The gun was then removed from the injector and replaced with the R28-2 gun.
* The SAD 2023 links below capture the planning for fixing these problems in thee R30-3 gun (which will then be version R30-4) and for installing it in May 2024.
+
* The SAD 2024 links below capture the planning for fixing these problems in the R30-3 gun (which will be version R30-4) and for installing it in May 2024.
 +
 
 +
 
 +
==R30-4 200 kV Gun SharePoint site==
 +
[https://jeffersonlab.sharepoint.com/:f:/s/CIS/Ejp9S0WdeXtPgFm_bwwkuEAB0gEzYKg7Ci0UfKK8qQnPfQ?e=1tfGAH R30-4 200 kV SharePoint site]
 +
 
 +
 
 +
Contains:
 +
* Pierce cathode end piece geometry and beam parameter space table
 +
* Notes, studies, and documentation
 +
* Electrostatics and beam dynamics modeling and simulation results
  
 
==R30-4 200 kV Gun SAD 2024 Planning Meetings==
 
==R30-4 200 kV Gun SAD 2024 Planning Meetings==
Line 12: Line 22:
 
* >[https://wiki.jlab.org/ciswiki/index.php/Jan_05_2024 Jan 05, 2024]
 
* >[https://wiki.jlab.org/ciswiki/index.php/Jan_05_2024 Jan 05, 2024]
 
* >[https://wiki.jlab.org/ciswiki/index.php/Jan_10_2024 Jan 10,2024]
 
* >[https://wiki.jlab.org/ciswiki/index.php/Jan_10_2024 Jan 10,2024]
 +
* >[https://wiki.jlab.org/ciswiki/index.php/Jan_17_2024 Jan 17, 2024]
 +
* >[https://wiki.jlab.org/ciswiki/index.php/Jan_24_2024 Jan 24, 2024]
 +
* >[https://wiki.jlab.org/ciswiki/index.php/Jan_30_2024 Jan 31, 2024]
 +
* >[https://wiki.jlab.org/ciswiki/index.php/Feb_7_2024 Feb 7, 2024]
 +
* >[https://wiki.jlab.org/ciswiki/index.php/Feb_14_2024 Feb 14, 2024]
 +
* >[https://wiki.jlab.org/ciswiki/index.php/Feb_21_2024 Feb 21, 2024]
 +
* [https://wiki.jlab.org/ciswiki/index.php/Feb_28_2024 Feb 28, 2024]
 +
* [https://wiki.jlab.org/ciswiki/index.php/Mar_6_2024 Mar 6, 2024]
 +
* [https://wiki.jlab.org/ciswiki/index.php/Mar_13_2024 Mar 13, 2024]
 +
* [https://wiki.jlab.org/ciswiki/index.php/Mar_20_2024 Mar 20, 2024]
 +
* [https://wiki.jlab.org/ciswiki/index.php/Mar_27_2024 Mar 27, 2024]
 +
* [https://wiki.jlab.org/ciswiki/index.php/Apr_03_2024 Apr 03, 2024]
 +
* [https://wiki.jlab.org/ciswiki/index.php/Apr_10_2024 Apr 10, 2024]
 +
* [https://wiki.jlab.org/ciswiki/index.php/Apr_17_2024 Apr 17, 2024]
 +
* [https://wiki.jlab.org/ciswiki/index.php/Apr_24_2024 Apr 24, 2024]
 +
* [https://wiki.jlab.org/ciswiki/index.php/May_1_2024 May 1, 2024]
  
 
==R30-3 200 kV Gun SAD 2023 Installation Links==
 
==R30-3 200 kV Gun SAD 2023 Installation Links==

Latest revision as of 13:48, 30 April 2024

  • The 200 kV gun (R30-3 with spherical electrode and 18" gun HVC) was installed in CEBAF during SAD 2023.
  • This gun performed as designed in terms of vacuum, and high voltage: no field emission at 200 kV after conditioning with Kr to ~240 kV.
  • It has two problems:
    • The beam waist is ~ 6 cm downstream of the GaAs wafer, compared to ~ 40 cm from the Tee electrode 14" HVC R28-2 gun operated in CEBAF for years at 130 kV.
    • It was a not possible to obtain the laser retro-reflection.
  • The gun was then removed from the injector and replaced with the R28-2 gun.
  • The SAD 2024 links below capture the planning for fixing these problems in the R30-3 gun (which will be version R30-4) and for installing it in May 2024.


R30-4 200 kV Gun SharePoint site

R30-4 200 kV SharePoint site


Contains:

  • Pierce cathode end piece geometry and beam parameter space table
  • Notes, studies, and documentation
  • Electrostatics and beam dynamics modeling and simulation results

R30-4 200 kV Gun SAD 2024 Planning Meetings

R30-3 200 kV Gun SAD 2023 Installation Links

R30-3 200 kV Gun SAD 2023 Planning Meetings

Links