Difference between revisions of "PQB Meeting September 10, 2015"
Jump to navigation
Jump to search
(Created page with "We will meet in TL 2236 Thursday September 10 at 1:00 pm EST. == For those calling in we'll use the Blue Jeans [https://cc.jlab.org/bluejeans] audio conference system. == P...") |
|||
(17 intermediate revisions by the same user not shown) | |||
Line 10: | Line 10: | ||
# Ed Folts: Hall A beamline progress report | # Ed Folts: Hall A beamline progress report | ||
− | # | + | # Jay Benesch: CEBAF Injector Upgrade |
+ | ## Original Accelerator Improvement Project (AIP) Charter (2010): [[media:INJ_Full_Energy_Injector_Upgrade_charter.pdf]] [[media:INJ_Full_Energy_Injector_Upgrade_charter.docx]] | ||
+ | ## Joe Grames, ''Considerations for CEBAF Injector Upgrade'': [[media:150824_Upgrade_Grames.pdf]] | ||
+ | ## Jay Benesch, ''Advanced Injector'': [[media:advanced_injector_PQB_10sep2015.pdf]] | ||
+ | |||
+ | |||
+ | |||
+ | |||
+ | ---- | ||
+ | |||
+ | '''Notes from this meeting:''' | ||
+ | |||
+ | * Hall A progress report: | ||
+ | # Modulation coils are in their right place. All work is complete and ready for test. | ||
+ | # There is plan to install the lumi detectors in Hall A beamline exit pipe. | ||
+ | # Cables for cavities on orders and will be pulled once they arrive. | ||
+ | # Working on installing the XYQ cavity set. | ||
+ | # Halo ladder installed with its QWeak targets and detector table is in place. Still Need to: | ||
+ | ## Re-design new targets | ||
+ | ## Install Qweak halo detectors | ||
+ | ## Pull cables (signal + HV) for the halo detectors. | ||
+ | |||
+ | |||
+ | * CEBAF Injector Upgrade: | ||
+ | # The new Quarter Cryo Module (QCM) will be installed and commissioned in the new Upgrade Injector Test Facility (UITF) in June 2016. | ||
+ | # Chopper maybe needed to clean the longitudinal space of the beam. | ||
+ | # We need to prepare a summary of PQB issues related to the injector. For each problem: symptoms, how it was measured or studied, and if a cause was found or suspected. |
Latest revision as of 09:24, 11 September 2015
We will meet in TL 2236 Thursday September 10 at 1:00 pm EST.
For those calling in we'll use the Blue Jeans [1] audio conference system.
Phone number: 1-888-240-2560 Meeting ID: 3528502673# Meeting URL: http://bluejeans.com/3528502673
Agenda:
- Ed Folts: Hall A beamline progress report
- Jay Benesch: CEBAF Injector Upgrade
- Original Accelerator Improvement Project (AIP) Charter (2010): media:INJ_Full_Energy_Injector_Upgrade_charter.pdf media:INJ_Full_Energy_Injector_Upgrade_charter.docx
- Joe Grames, Considerations for CEBAF Injector Upgrade: media:150824_Upgrade_Grames.pdf
- Jay Benesch, Advanced Injector: media:advanced_injector_PQB_10sep2015.pdf
Notes from this meeting:
- Hall A progress report:
- Modulation coils are in their right place. All work is complete and ready for test.
- There is plan to install the lumi detectors in Hall A beamline exit pipe.
- Cables for cavities on orders and will be pulled once they arrive.
- Working on installing the XYQ cavity set.
- Halo ladder installed with its QWeak targets and detector table is in place. Still Need to:
- Re-design new targets
- Install Qweak halo detectors
- Pull cables (signal + HV) for the halo detectors.
- CEBAF Injector Upgrade:
- The new Quarter Cryo Module (QCM) will be installed and commissioned in the new Upgrade Injector Test Facility (UITF) in June 2016.
- Chopper maybe needed to clean the longitudinal space of the beam.
- We need to prepare a summary of PQB issues related to the injector. For each problem: symptoms, how it was measured or studied, and if a cause was found or suspected.