Difference between revisions of "October 12, 2016 - 4-Laser/LLRF Monthly Status Meeting"
Jump to navigation
Jump to search
(Created page with "Agenda 1. Tomasz - LLRF update 2. Software Request to switch laser/LLRF between 250/499 MHz * Request document media:161012_4Laser4LLRF.docx 3. Schedule [http://opsweb....") |
|||
Line 1: | Line 1: | ||
− | Agenda | + | '''Agenda''' |
1. Tomasz - LLRF update | 1. Tomasz - LLRF update | ||
− | 2. Software Request to switch laser/LLRF between 250/499 MHz | + | 2. Software Request to switch laser/LLRF between 250/499 MHz [[media:161012_4Laser4LLRF.docx]] |
− | |||
− | 3. Schedule [http://opsweb.acc.jlab.org/TJ3/12GeV_CEBAF/WSAD2016.html Winter SAD Schedule] | + | 3. Proposed Installation Schedule [http://opsweb.acc.jlab.org/TJ3/12GeV_CEBAF/WSAD2016.html Winter SAD Schedule] |
* There are ~3 weeks in January for this job: Jan 3 (return to work) to Jan 27 (CEBAF restoration) | * There are ~3 weeks in January for this job: Jan 3 (return to work) to Jan 27 (CEBAF restoration) | ||
− | * Week 1 - Install LLRF, connect lasers when makes sense, test ability to move between 250/500, verify proper power levels to lasers, and check reproducibility. | + | * Week 1 (Jan 4-11) Install LLRF, connect lasers when makes sense, test ability to move between 250/500, verify proper power levels to lasers, and check reproducibility. |
− | * Week 2 - Injector lock-ups and make e-beam, test against rf sensitive elements like bunchers, chopper, and unit when 2K is restored. | + | * Week 2 (Jan 12-18) Injector lock-ups and make e-beam, test against rf sensitive elements like bunchers, chopper, and unit when 2K is restored. |
− | * Week 3 - Evaluate and make sure front end is performing well, finalize/rectify outstanding issues, worst case backout. | + | * Week 3 (Jan 19-25) Evaluate and make sure front end is performing well, finalize/rectify outstanding issues, worst case backout. |
Revision as of 09:54, 12 October 2016
Agenda
1. Tomasz - LLRF update
2. Software Request to switch laser/LLRF between 250/499 MHz media:161012_4Laser4LLRF.docx
3. Proposed Installation Schedule Winter SAD Schedule
- There are ~3 weeks in January for this job: Jan 3 (return to work) to Jan 27 (CEBAF restoration)
- Week 1 (Jan 4-11) Install LLRF, connect lasers when makes sense, test ability to move between 250/500, verify proper power levels to lasers, and check reproducibility.
- Week 2 (Jan 12-18) Injector lock-ups and make e-beam, test against rf sensitive elements like bunchers, chopper, and unit when 2K is restored.
- Week 3 (Jan 19-25) Evaluate and make sure front end is performing well, finalize/rectify outstanding issues, worst case backout.