Difference between revisions of "CEBAF Injector Upgrade"
Jump to navigation
Jump to search
Line 21: | Line 21: | ||
:[[WF Wien Filters (200 kV upgrade)]] - Wien filters are upgraded with new coils (20 A) and new high voltage (+/- 18 kV) for operation at 200 keV | :[[WF Wien Filters (200 kV upgrade)]] - Wien filters are upgraded with new coils (20 A) and new high voltage (+/- 18 kV) for operation at 200 keV | ||
:[[QW Wien quadrupoles (200 kV upgrade)]] - New quadrouple are designed for higher 200 keV energy, but also of improved magnetic design w/ minimized dipole component | :[[QW Wien quadrupoles (200 kV upgrade)]] - New quadrouple are designed for higher 200 keV energy, but also of improved magnetic design w/ minimized dipole component | ||
+ | :[[Chopping System (200 kV upgrade)]] | ||
+ | |||
:[[200KV gun BPM's]] | :[[200KV gun BPM's]] | ||
Line 27: | Line 29: | ||
:[[Prebuncher]] | :[[Prebuncher]] | ||
:[[Pre-buncher cavity (200 kV upgrade)]] | :[[Pre-buncher cavity (200 kV upgrade)]] | ||
− | |||
− | |||
− | |||
− | |||
::[[Vacuum Upgrades]] | ::[[Vacuum Upgrades]] | ||
− | |||
::[[A1 Aperture Motor Control]] | ::[[A1 Aperture Motor Control]] | ||
Revision as of 13:17, 27 August 2020
This area is related to Injector Upgrade Meetings
Injector upgrade calendar
- Run (now - May 6)
- Phase 1 (May 6 - end of 2020)
- Run (Jan 2021 - Sep 13 2021)
- Phase 2 (Sep 13 - end of 2021)
Injector Upgrade Meetings
Link to AIPINJ OneDrive folder
AIPINJ Layouts
Injector Upgrade Documents and Links
Upgrade Components
- DR dipole (15 deg) - New 15 deg air core bend dipole replaces pre-existing DS dipole
- FX beamline and FY chopper solenoids - New double-coil sw/cw capable solenoids with 38 mm (FX) and 46 mm (FY) ID
- PSS Kicker (upgraded for 200 kV upgrade) - New PSS kicker has been designed to operate at higher momentum and with more reliable design
- WF Wien Filters (200 kV upgrade) - Wien filters are upgraded with new coils (20 A) and new high voltage (+/- 18 kV) for operation at 200 keV
- QW Wien quadrupoles (200 kV upgrade) - New quadrouple are designed for higher 200 keV energy, but also of improved magnetic design w/ minimized dipole component
- Chopping System (200 kV upgrade)
ATLIS Tasks
AIPINJ
- PSS Injector Segment PLC Upgrade
- Injector Camac to Vme and camera upgrade
- Pedestal Location Surveys
- Install Chopper SSA's
- Chopper SSA LCW
- Penetration Drops
- Testing Wien HV Controls at UITF
- Accelerator network re-survey
- Remove and re-install BPM's Gun to chopper
- Install new IPM2I03
- Remove and calibrate current monitoring electronics
- Harp work
Non-AIPINJ
- New Gun2 loading chamber
- Placeholder for Tim Minga to test laser room smoke detector alarm to MCC/Guard