Difference between revisions of "Meeting 3/31/22 - COMTRA"
Jump to navigation
Jump to search
Line 2: | Line 2: | ||
; Eric's plan at IJCLab for crystals | ; Eric's plan at IJCLab for crystals | ||
+ | * Hall A detectors NaI(Tl?) [[media:220331_HallA_NaI.jpg]] | ||
; DAQ status | ; DAQ status |
Revision as of 07:56, 31 March 2022
Agenda
- Eric's plan at IJCLab for crystals
- Hall A detectors NaI(Tl?) media:220331_HallA_NaI.jpg
- DAQ status
- Magnet status
- Steel inventory media:220324_Steel.jpg
- Steel report media:Compton_East Carolina Metal treatment metallurgy_3_24_2022.pdf
- Sandesh preliminary media:UPDATE 1 -COMPTON POLARIZED TARGET MAXWELL Field analysis 032522.pptx
- UITF plan
- April - finish design & assembly of Wien and Mott hardware, finish 200 KV HV vac work,
- May - install Wien/Mott UITF, finish 200 KV gun assembly, restore polarized laser UITF
- June - install 200 keV gun, bake, big job, goal is making beam by ~July 4th weekend
- July - make 200 keV polarized beam, calibrate the Mott, using ~nA beam and U-Wien
- Aug - install Compton in MeV section, run keV beam as needed
- Sep/Oct - calibrate Compton, two separate ~week long runs
- Wien/Mott layouts