March 14, 2019 - Weekly AIPINJ Meeting

From Ciswikidb
Revision as of 07:41, 14 March 2019 by Grames (talk | contribs)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search
200kV Gun

Status update as of monday, march 11

  • fasteners: ordered and due march 6th. received and in my cubicle.
  • .015" wire: received and handed over.
  • sapphire roller: ordered and due april 12th. we have 2 in 1137, plus 2 rollers supposedly shipped friday.
  • alumina centering ring: ordered and due april 12th. we have 1 in 1137
  • roller pin: machine shop working, requested due date of march 15th? we have 3 in 1137
  • roller spring: machine shop working, requested due date of march 15th but will be late. material won't be in until next week. shop was slow in resolving vendor and material issues. submitted february 8th, resolved and signed off february 27th. we have 3 in 1137
  • key: received and handed over.
  • aft end: machine shop working with requested due date of march 15th? shop says on schedule.
  • ring holder: received and handed over.
  • black insulator on 10" flange welded, leak checked, new flange w/ fiducials, worth a survey before mounting electrode?
  • Status of small shed cathode electrode polished, degassed?
Solenoid Update
Wien Filter Update
  • Gabriel status update
Spring SAD (April 15 - June 10)
Latest Layouts