- Pre-planning for Aug-Nov SAD 2019
- media:190501_GunUpgradeJobs.docx
- media:30July2019_KryptonLine.pptx
- Gun2 Load Lock Chamber Replacement
- Beam studies before SAD begins
- Gun2 HV chamber jobs
- S&A job for new small shed going into CEBAF
- ATLIS to remove small shed from UITF and prep for CEBAF
- Gun2 200kV cathode, 10kV anode, kr plumbing
- Pete's BPM Atlis
- CEBAF Kr Gas HV Conditioning
- Logbook entry of 200 kV cathode assembly
- Gun2 Load chamber jobs
- Laser jobs
- Make beam again jobs
- Activate a photocathode
- Remove, inspect, install FC2
- Testing CEBAF w/ 200 keV beam
- AIPINJ
- Last SAD before upgrade
- Walk throughs and measurements
- Remove oil tank
- SAD Schedule and Beam Resstoration
- PQB - SAD & CREX