June 11, 2020 - ME/INJ/CIS/CASA

From Ciswikidb
Revision as of 06:57, 11 June 2020 by Grames (talk | contribs) (Created page with "== Meeting Info == We will meet Thursday @ 10am EDT <u>'''via BlueJeans'''</u> Meeting URL (for video and/or audio call in): https://bluejeans.com/909497334 Phone number (f...")
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search

Meeting Info

We will meet Thursday @ 10am EDT via BlueJeans
Meeting URL (for video and/or audio call in): https://bluejeans.com/909497334
Phone number (for audio call in): 1-888-240-2560
Meeting ID: 909497334#

Week of June 11

2I region NEG tube assembly jobs
Wien filter / magnet mapping
Y-chamber survey, NEG flange
A1/A2 girder
...and more!


Last week June 4

Magnets...

MFX Solenoids (ETI)
  • Waiting on update on the measurements of the 1st solenoid.
  • The 2nd solenoid coils completed and passed all electrical testing.
  • In process of winding coils for the 3rd solenoid.
15 deg. bend dipole (Milhous)
  • Coil tooling is ready.
  • Coil winding will proceed week of JUN8 (when winding machine becomes available).
  • Discussing their QA process with the coils.
  • Gathered documentation on the magnet from the PR and emails.

We'll go back to work next week....

Last week May 28 talking points

Plan for the upcoming SAD and injector rebuild (Grames, Adderley, Marcy, Carlos, , Bubba, Windham)

  • a. Long list of jobs for new NEG BPM's here: https://wiki.jlab.org/ciswiki/index.php/200KV_gun_BPM%27s
  • b. Capture new solenoid on NEG pipe, NEG coat them too
  • c. Assemble new Y-chamber on girder, new bottom flange, new NEG's, finish coating that chamber
  • d. Setup vacuum chamber if Caryn is going to evaluate any windows
  • e. First or second, provide UITF Wien magnet to Meyers (Phil), hi-pot and map 3 coils pairs
  • f. Second or first, rebuild UITF Wien internals to eliminate high E-points (Bubba), finalize spacers/springs/gap (Carlos/Danny remotely)
  • g. Setup rebuilt Wien in UITF and HV test (Carlos)
  • h. Work w/ Shaun to test top-hats and garage needed for John's y-chamber design
  • i. Collect up dozens of vacuum parts, clean, and get ready for SAD (pipes, bellows, top-hats)
  • j. Work w/ Danny/Shaun/S&A to fabricate and assemble new A2 aperture on a cube
  • k. Work w/ Scott to assembly dummy of motorized A1 on new cube, ready for shutdown
  • l. 11 Collect up all the girders, supports, hardware
  • m. Build two prebuncher cavities?
  • n. Work w/ shop to capture Wien quads on crosses, weld on flanges, for tunnel viewers
  • o. Build up and vacuum test the y chamber: RGA, base pressure
  • p. Build up and test the docking chamber as needed (won’t be needed until later in the shutdown)


Last Week's Talking Points - May 21

Modeling
Solenoid
  • Progress!
First coat of green paint on "core"
Y/Laser chamber viewers
  • Design status
Wien Filter
From Mike Beck - The 6 new "Wien" coils meet dimensional check acceptance criteria and counted turn count all as required at 2 layers x 13 turns per. Will put spread sheet with dimensional data together in coming days. Also, checked resistance on all 6, the range was consistent at ~.2 ohms. The visual quality of coils that Technicoil provided are nice in appearance.  Will conduct hipot testing when able to get back onsite and confirm the rest of QA acceptance testing, fit to core (when core arrives), and mapping required.
Wien coils in crate at MMF
MHD A1/A2 Steering Coils
PSS Kicker
  • ME model status
  • Getting quotes (2-4)
Wien quads
  • CED from Gary Croke => MQW: B'L = 15 G/A with +/- 3A limits
Songsheets
  • Will circulate when done