Phase 1 - HCO & Commissioning
Revision as of 13:52, 15 March 2021 by Moser (talk | contribs) (→System Readiness / HCO Schedule (Apr 5 - Apr 30))
CIS Jobs Leading to HCO & Commissioning (Jan 1 - Apr 30)
- 15 deg dipole (Scott)
- (Scott working with CAD/DCG) Update drawings and document
- Laser jobs (Shukui/Scott)
- (Shaun...) Complete outrigger box, install, test with laser room shutter
- (Shukui) Update LSOP
- (Shukui/Amali) Install/align Pockels cell
- (Shukui) Re-install Hall B amp in permanent location
- (Scott) Complete macropulse chassis upgrade, test all beam modes
- Gun HVPS jobs (Carlos/Bubba/Scott)
- (Bubba/Phil by 3/9) Re-install bracket
- (Carlos/Bubba by 3/9 DONE) Regrease ceramic after bake
- (Scott/Joe after PSS HV cert) Remove old HV parts (150kV glassman, old HV interlock chassis, VME interface card)
- (Scott/Joe working...) Pull additional Anode bias HV cable near Glassman rack
- (Draft done) Develop HV commissioning plan/staffing Media:Gun2 Tee electrode 200kV HV codnitoning plan 2021 draft01.pptx
- (Carlos) Guidelines for ramping the gun voltage / HV conditioning to (>?) 130 kV under VACUUM conditions. Media:CEBAF Gun HV processing guidelines March 2021.docx
- Wien HVPS
- (Tony/Carlos) Drop/pull HV cables from HV switcher outputs to Wiens
- (Riad) InjSteer screens check/test with Gary and Michelle updates with HVPS and new PS epics values, tested, ready
- (Carlos wrap up with engineering) drawings, document
- Ion Pump Power Supplies media:210209_ion pump names.xlsx
- (Scott) Re-install (2) HV patch boxes, update box labels, pull HV drop cables to patch boxes, updated labels
- (Scott) Update screens, labels, drawings, document
- Vacuum
- (Marcy/Phil) A1/A2 : Install, leak check, bake, leak check
- (Marcy/Phil) Wien : Install, leak check, bake, leak check
- (Marcy) Add extractor gauge to y chamber port
- (Marcy) Fab cable for Y-NEG activation
- (Marcy/Phil) Activate DP can downstream FC#1
- (Marcy) Set final IP voltages (no FE'ers)
- (Joe test by 3/12) see if cathode activates in prep chamber. If not, bake (No water in RGA scan)
- Valves
- (Scott) HCO UHV vacuum fault
- (Scott) Update drawings, labels, document
- Air, GN2, LCW
- (Phil/Bubba) Fabricate, install air manifold w/ cutoff for (8) viewers, (2) valves, (2) spares
- (Ricky to fasten) Fasten LCW to pedestals
- Crash inhibit
- (Tony/Phil) Install, test crash inhibit for pcup and viewer (note - fail safe test, i.e. do NOT hook up air to BOTH devices)
- (Tony/Phil) Install, test crash inhibit for harp and viewer (note - does this exist, would speak to I&C early on)
- Apertures & PCup
- (Scott after bake) Terminate A1 cable, drive motor, test shoulder bolt
- (Phil) Put new scribed aperture stops in bag in tunnel
- (Pete/Phil) Attach current monitoring w/ inline I&C protection boxes
- (Pete/Phil) Reconnect LCW, I&C check flow meters clear interlock
- Electrician jobs
- (Electricians/Scott) Bond girders
- (Scott working on this) Install cable tray on girders
- Decarad
- (Scott) Install/cable 1 chassis, (5) for Carlos, (5) for Joe
I&C/Software Jobs Leading to HCO & Commissioning (Apr 5 - Apr 30)
- I&C Jobs
- What to expect in tunnel?
- Similar mechanical layout => Gun + 3 girders (Y + Wien + A1/A2)
- There is now a 3D CAD model from gun to chopper, I can share pics or see Gary Hays or Shaun Gregory
- Similar utilities => LCW (A1/A2) + Air (Bubba/Phil) + Cable tray (above/below) + 3 cable drops (Y, Laser, Chopper)
* BPMs = Pete estimates 1 person x 5 days for all of the BPM hook-up and pre-beam checkout jobs
- 10 total - all unrotated
- 3 new style => NEG coated large bore (2.5" ID); mapped by Musson (Kx/Ky values available)
- 7 old style => 5.5" long end tapped
- Viewers
- 8 total - all chromox except ITV0I02 (YAG)
- Crash inhibit #1 : ITV0I01 and Polarized Cup IFY0I01
- Crash inhibit #2 : ITV0I02 and Harp IHA0I02
- Harps
- 1 total - IHA0I02 (YAG), on same cross as viewer ITV0I02 (requires crash inhibit)
- Wien HV
- Tony status update
* Current Monitoring - Pete estimates 1 person x 3 days for ItoV, Picoammeters, Gun FSD LCW waterflow interlocks)
- 3 total - same as before (PCUP, A1, A2)
- PCUP identical as before, just a new location
- A1 current monitoring as before, linear bellow motion now has STAC5 motor (so remote or manual; has 3 stop positions
- A2 current monitoring as before, linear bellows manual as before; has 3 stop positions. Used by PSS group for kicker
- Valves
- 3 total - all have in-line EPICS shut over ride capability (CIS installs this box)
- Gun valve - VBV2I01A (new name), otherwise same all metal gate valve
- Beam line valve - VBV1I07 (same name), same all metal gate valve
- Beam line valve - VBV0I02 (same name), but now all metal gate valve, requires cable terminations like VBV1I07
- All 3 valves tied to UHV vacuum fault (100 uA limit)
- Ion pumps
- Marcy's final list media:210209_ion pump names.xlsx
- Software Jobs
- CED
- Michele or Gary can gives us an update
- Apps
- Injector steering script getting upgrades for Wien/Solenoid controls, also needs update of correctors/bpms
- Any script that refers to CED elements from Gun to Chopper will need name review, sounds like a big job
- Screens
- I guess many screens auto-updated from CED, that's great
- Like with apps, will need name review; I guess system owners look at their own screens for oddities?
- What else for software?
Magnet/DC-Power/Software Jobs Leading to HCO & Commissioning (Apr 5 - Apr 30)
- DC/Magnet Jobs
- Spreadsheet updated after further feedback media:210301_Phase1_Magnet_Summary_v3.xlsx
- Spreadsheet updated at 3/1 SAD planning meeting media:210301_Phase1_Magnet_Summary_v2.xlsx
- Spreadsheet initially media:210301_Phase1_Magnet_Summary.xlsx
- Software Jobs
- CED
- Apps
- Screens
- What else for software?
- Other magnet jobs
- (JM) Complete magnet table I circulated
- (JM/LL) Initial QW measurement and assessment (sufficient for CED), summarized for Gary
- (RS/GC) FG solenoid special hysteresis for Gary
- (RS/MJ) Magnet info for Inj Steer spin calculations
- (JM/JG) Decision on spare DR fabrication and alignment
- (LL/JK/JM) PSS kicker - does MMF have any responsibility here, maybe just PSS?
- (LL/JM) Second QW measurement, what's the scope here?
- (JM) When is the rotating coil stand ready?
- (JM/LL) Reconciling MHD discrepancy
- (LL) Report on QW
- (LL) Report on HD
- (LL) Report on PSS kicker
System Readiness / HCO Schedule (Apr 5 - Apr 30)
Format: time: System (# of people)
April | Mon | Tue | Wed | Thu | Fri | Sa | Su |
---|---|---|---|---|---|---|---|
5th - 9th | 5a-noon: BPMs (1x) 5a-noon: Viewers (1x) 8a-4p: DC Power (2x) |
5a-noon: BPMs (1x) 5a-noon: Viewers (1x) 8a-4p: DC Power (2x) |
5a-noon: BPMs (1x) 5a-noon: Viewers (1x) 8a-4p: DC Power (2x) |
5a-noon: BPMs (1x) 8a-4p: DC Power (2x) |
5a-noon: BPMs (1x) 8a-4p: DC Power (2x) |
Sa | Su |
12th - 16th | 5a-noon: ItoV/Pico/GunFSD (1x) 8a-4p: DC Power (2x) |
5a-noon: ItoV/Pico/GunFSD (1x) 8a-4p: DC Power (2x) |
5a-noon: ItoV/Pico/GunFSD (1x) 8a-4p: DC Power (2x) |
8a-4p: DC Power (2x) | 8a-4p: DC Power (2x) | Sa | Su |
19th - 23rd | M | T | W | R | F | Sa | Su |
26th - 30th | Swings: PSS beamline Certs? | Swings: PSS beamline Certs? | Swings: PSS beamline Certs? | R | F | Sa | Su |
- BPM = Francis
- Viewers = Norris
- Harps = Dela Cruz
- DC Power = Coleman, others in group; heavily in afternoons
Beam Commissioning (May 3 - Jul 2)
Important Dates
updated 3/15/21
- Finalize commissioning plan: April 5th
- Injector HCO/SR Complete: 5/2
- Injector Beam Commissioning Begins: 5/3
- NL/Inj -> Stable 2K: 5/21
- Full CEBAF PSS Certification: 5/24 - 6/11
- End of SAD: 7/2
- Resumption of Physics: Mid-August
ATLis Testplans
updated 3/1/21
- 21911 Gun high voltage conditioning
- 21923 Perform 130keV emittance measurements and matching as part of Injector Upgrade commissioning
Activities
updated 3/15/21