Sep 08, 2021 - Group Meeting
Jump to navigation
Jump to search
2022 Winter SAD ATLIS Tasks
Phase 1 Region
- Install 200 kV w/o field emission
- Replace DR dipole => PO written week of Aug 30 for new DM at CEBAF, UITF and 2 spare coils
- Replace noisy Wien 20A SCE =>
- Repair leaky PCUP LCW fitting
- Remake A2 joint
- Replace harp
- Install & test 200 kV kicker
- Phase 2 Region
- Possibly install solenoid/valve downstream of chopper => MMF mapping solenoids in Sep. Do we have 2-3/4" pneumatic beam line valve?
- Install bright lighting => Walked area with FM. Waiting for follow-up.
CEBAF 200 kV Gun
- Carlos - Status of small gun HV limits, CEBAF and UITF
- Carlos - GTS gun HV design, i.e. reaching >200 kV w/o field emission
- Gabriel - Picking the anode to eliminate kick