MOLLER PQB Meeting September 4, 2024

From Ciswikidb
Revision as of 13:33, 11 September 2024 by Suleiman (talk | contribs)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search

In person in MCC Conference Room and with Zoom.

https://wiki.jlab.org/ciswiki/index.php/Parity_Quality_Beam

--


Agenda:


  • Reminder: Accelerator MOLLER Project Meeting is on Monday September 9th, 3-4 pm


  • Injector Upgrade Progress:
  1. Gun was conditioned to 200 kV without field emission
  2. Beam tests showed excellent beam quality and good transmission at 100 μA: media:R30-4_gun_beam_comm.pdf media:R30-4_gun_beam_comm.pptx
  3. RTP new HV Driver full system testing started this week


  • Beam Study Results:
  1. FFB/FF in Hall A:
    1. May beam test, FFT and width, Xiang Zhang: media:2024May_FFBtest_Results.pdf
    2. Check FFB ON versus OFF in QWeak data
    3. 2010 QWeak Data: [1]