'''Notes from this meeting:''' | '''Notes from this meeting:''' | ||
− | * | + | * Superheated fluid will be C<sub>2</sub>F<sub>6</sub> |
− | * Beam | + | * Beam Energy Tasks: |
− | # Analyse | + | # Analyse beam energies used during September 2015 Bubble Chamber Run I similar to what Grames did for Mott run. |
+ | # Measure the stray field in 5D line (Bubble Chamber) since new steel was added between 5D00 and 5D01 BPMs and to extend measurement to radiator. | ||
+ | # Use installed Hall Probe to study systematic error in beam energy measurement (0.01% accuracy, resolution to 2 ppm, and a temperature stability of 10 ppm/°C). | ||
+ | |||
+ | * Temporary Operational Safety Procedure (TOSP) expired on December 8, 2015. Needs new approval with updates on modifications: no mercury, new collimator, new lead camera shielding. |
Revision as of 19:09, 9 March 2016
We will meet in TL 2221 on Wednesday March 9 at 3:30 pm EST.
For those calling in we'll use the Blue Jeans [1] audio conference system.
Phone number: 1-888-240-2560 Meeting ID: 3528502673# Meeting URL: http://bluejeans.com/3528502673
Agenda:
1- New Test Run II Schedule:
- Bubble Installation: May 5 – May 12, 2016
- Bubble Run: June 13 – June 27, 2016
2- Test Run III: Aug 15 – Aug 29, 2016
3- Beam Analysis: energy and position – energy spread and beam size
- Beam Energy:
- media:160309_MottEnergy_Grames.pdf media:160309_MottEnergy_Grames.pptx
- media:JLab-TN-16-xx_v5.pdf media:JLab-TN-16-xx_v5.docx
4- Bubble Chamber work at ANL: media:Progress_March_2016_Bubble_Chamber.pdf
5- Measuring 19F(γ,α)15N in June 2016: media:Fluorine_June2016_Test_part2.pdf media:Fluorine_June2016_Test_part2.pptx
6- New beamline design with sweep magnet
Notes from this meeting:
- Superheated fluid will be C2F6
- Beam Energy Tasks:
- Analyse beam energies used during September 2015 Bubble Chamber Run I similar to what Grames did for Mott run.
- Measure the stray field in 5D line (Bubble Chamber) since new steel was added between 5D00 and 5D01 BPMs and to extend measurement to radiator.
- Use installed Hall Probe to study systematic error in beam energy measurement (0.01% accuracy, resolution to 2 ppm, and a temperature stability of 10 ppm/°C).
- Temporary Operational Safety Procedure (TOSP) expired on December 8, 2015. Needs new approval with updates on modifications: no mercury, new collimator, new lead camera shielding.