Line 17: Line 17:
 
3- Beam Analysis: energy and position – energy spread and beam size
 
3- Beam Analysis: energy and position – energy spread and beam size
 
* Beam Energy:
 
* Beam Energy:
: [[media:160409_MottEnergy_Grames.pdf]] [[media:160409_MottEnergy_Grames.pptx]]
+
: [[media:160309_MottEnergy_Grames.pdf]] [[media:160309_MottEnergy_Grames.pptx]]
: [[media:JLab-TN-16-xx_v5.pdf]] [[media:JLab-TN-16-xx_v5.docx]]
+
: [[media:JLab-TN-16-xx_v6.pdf]] [[media:JLab-TN-16-xx_v6.docx]]
  
 
4- Bubble Chamber work at ANL: [[media:Progress_March_2016_Bubble_Chamber.pdf]]
 
4- Bubble Chamber work at ANL: [[media:Progress_March_2016_Bubble_Chamber.pdf]]
  
 
5- Measuring <sup>19</sup>F(γ,α)<sup>15</sup>N in June 2016: [[media:Fluorine_June2016_Test_part2.pdf]] [[media:Fluorine_June2016_Test_part2.pptx]]
 
5- Measuring <sup>19</sup>F(γ,α)<sup>15</sup>N in June 2016: [[media:Fluorine_June2016_Test_part2.pdf]] [[media:Fluorine_June2016_Test_part2.pptx]]
 
6- New beamline design with sweep magnet
 
  
  
Line 33: Line 31:
 
'''Notes from this meeting:'''
 
'''Notes from this meeting:'''
  
* We will use C<sub>2</sub>F<sub>6</sub>
+
* Superheated fluid will be C<sub>2</sub>F<sub>6</sub>
 +
 
 +
* Beam Energy Tasks:
 +
# Analyse beam energies used during September 2015 Bubble Chamber Run I, similar to what Grames did for Mott run.
 +
# Measure stray field in 5D line (Bubble Chamber) since new steel was added between 5D00 and 5D01 BPMs and to extend measurement to radiator.
 +
# Use Hall Probe installed inside dipole to study systematic errors (especially magnet power supply) in beam energy measurement (0.01% accuracy, resolution to 2 ppm, and a temperature stability of 10 ppm/°C).
 +
 
 +
* Measure <sup>19</sup>F(γ,α)<sup>15</sup>N around 5.4 MeV electron kinetic energy to map huge change in rate in this region. Develop a procedure to enable running below 1 nA beam currents.
  
* Beam energy Tasks:
+
* Temporary Operational Safety Procedure (TOSP) expired on December 8, 2015. Needs new approval with updates on modifications: no mercury, new collimator, new lead camera shielding.
# Analyse Sept data
 

Latest revision as of 10:13, 10 March 2016

We will meet in TL 2221 on Wednesday March 9 at 3:30 pm EST.

For those calling in we'll use the Blue Jeans [1] audio conference system.

Phone number: 1-888-240-2560
Meeting ID: 3528502673#
Meeting URL: http://bluejeans.com/3528502673


Agenda:

1- New Test Run II Schedule:

  1. Bubble Installation: May 5 – May 12, 2016
  2. Bubble Run: June 13 – June 27, 2016

2- Test Run III: Aug 15 – Aug 29, 2016

3- Beam Analysis: energy and position – energy spread and beam size

  • Beam Energy:
media:160309_MottEnergy_Grames.pdf media:160309_MottEnergy_Grames.pptx
media:JLab-TN-16-xx_v6.pdf media:JLab-TN-16-xx_v6.docx

4- Bubble Chamber work at ANL: media:Progress_March_2016_Bubble_Chamber.pdf

5- Measuring 19F(γ,α)15N in June 2016: media:Fluorine_June2016_Test_part2.pdf media:Fluorine_June2016_Test_part2.pptx




Notes from this meeting:

  • Superheated fluid will be C2F6
  • Beam Energy Tasks:
  1. Analyse beam energies used during September 2015 Bubble Chamber Run I, similar to what Grames did for Mott run.
  2. Measure stray field in 5D line (Bubble Chamber) since new steel was added between 5D00 and 5D01 BPMs and to extend measurement to radiator.
  3. Use Hall Probe installed inside dipole to study systematic errors (especially magnet power supply) in beam energy measurement (0.01% accuracy, resolution to 2 ppm, and a temperature stability of 10 ppm/°C).
  • Measure 19F(γ,α)15N around 5.4 MeV electron kinetic energy to map huge change in rate in this region. Develop a procedure to enable running below 1 nA beam currents.
  • Temporary Operational Safety Procedure (TOSP) expired on December 8, 2015. Needs new approval with updates on modifications: no mercury, new collimator, new lead camera shielding.