Difference between revisions of "July 11,, 2019 - Weekly AIPINJ Meeting"
Jump to navigation
Jump to search
(One intermediate revision by the same user not shown) | |||
Line 6: | Line 6: | ||
:May-Oct ~ 6 months to rebuild the 200keV beam line (gun, chopper, up to QCM) | :May-Oct ~ 6 months to rebuild the 200keV beam line (gun, chopper, up to QCM) | ||
:Nov ~ Booster/QCM swap between CEBAF/UITF | :Nov ~ Booster/QCM swap between CEBAF/UITF | ||
− | :Dec-Jan ~ Install and instrument | + | :Dec-Jan ~ Install and instrument Booster at CEBAF, cool and SRF testing |
− | |||
:Feb-Mar ~ Commissiong 10 MeV beam to FC2, ILD? | :Feb-Mar ~ Commissiong 10 MeV beam to FC2, ILD? | ||
Line 14: | Line 13: | ||
;Simulations | ;Simulations | ||
+ | * elegant layout gun to QCM by ~ end of July | ||
+ | * gpt ~ goals are? |
Latest revision as of 09:53, 11 July 2019
Agenda
- Schedule
- Whiteboard pic media:190711_down.jpg
- Suggests installation & commissioning plan like this:
- May-Oct ~ 6 months to rebuild the 200keV beam line (gun, chopper, up to QCM)
- Nov ~ Booster/QCM swap between CEBAF/UITF
- Dec-Jan ~ Install and instrument Booster at CEBAF, cool and SRF testing
- Feb-Mar ~ Commissiong 10 MeV beam to FC2, ILD?
- Layout/Tasks
- Simulations
- elegant layout gun to QCM by ~ end of July
- gpt ~ goals are?