*Gabriel status update
 
*Gabriel status update
 +
*Wien spin calculation examples for 100kV, 200kV, 350kV, 5MeV, 6.3MeV [[media:190307_SpinCalculator.xlsx]]
  
 
;Latest Layouts
 
;Latest Layouts

Latest revision as of 10:57, 7 March 2019

Topics

200kV Gun
  • fasteners: ordered and due march 6th.
  • .015" wire: received and handed over.
  • sapphire roller: ordered and due april 12th.
  • alumina centering ring: ordered and due april 12th.
  • roller pin: machine shop working, requested due date of march 15th?
  • roller spring: machine shop working, requested due date of march 15th but will be late. material won't be in until next week. shop was slow in resolving vendor and material issues. submitted february 8th, resolved and signed off february 27th.
  • key: received and handed over.
  • aft end: machine shop working with requested due date of march 15th?
  • ring holder: received and handed over
  • Status of small shed cathode electrode
Spring SAD (April 15 - June 10)
Wien Filter
Latest Layouts