(Created page with "===200kV Gun=== * Task and Timeline Gantt chart => media:170421_CHG.pdf ===325kV Gun .... WHAT ?!?!?=== * media:170519_325kV_simulations.pdf => Did we talk about this...") |
|||
Line 6: | Line 6: | ||
===Gun2 NEG Tube=== | ===Gun2 NEG Tube=== | ||
− | + | : We are making 4 BPM's | |
− | : | + | : Shop has materials now and machining (#327755) |
− | + | : Phil will pick up for weld, 400C bake, leak check, clean, NEG coat | |
− | : | + | : Pete will perform optical/electrical checks |
− | + | : John will perform Gabou map | |
− | + | ::Final NEG tube design => [[media:NEGTUBE_MAY03.pdf]] | |
− | |||
− | |||
− | |||
− | |||
− | |||
− | : | ||
− | :: | ||
− | |||
− | |||
− | |||
− | |||
::M20 Old Assembly Modification [[media:0990.pdf]] | ::M20 Old Assembly Modification [[media:0990.pdf]] | ||
::M20 New Assembly Can [[media:0991.pdf]] | ::M20 New Assembly Can [[media:0991.pdf]] | ||
::M20 New Assembly 6.00 x 4.500 reducer flange[[media:0.992.pdf]] | ::M20 New Assembly 6.00 x 4.500 reducer flange[[media:0.992.pdf]] | ||
− | |||
− | |||
− | |||
− | |||
− | |||
===Gun3 Removal and Diagnostics Chamber Installation === | ===Gun3 Removal and Diagnostics Chamber Installation === | ||
− | + | : Second bake and activate week of May 30th => [http://opsweb.acc.jlab.org/CSUEApps/atlis/task/17278 Remove and replace Gun3 ATLIS task] | |
− | : | + | : Remove VBV3I02 from special interlock and swap PLC for relays |
− | |||
− | |||
− | |||
− | |||
− | |||
===Spellman HVPS update=== | ===Spellman HVPS update=== |
Revision as of 20:33, 25 May 2017
200kV Gun
- Task and Timeline Gantt chart => media:170421_CHG.pdf
325kV Gun .... WHAT ?!?!?
- media:170519_325kV_simulations.pdf => Did we talk about this last week?
Gun2 NEG Tube
- We are making 4 BPM's
- Shop has materials now and machining (#327755)
- Phil will pick up for weld, 400C bake, leak check, clean, NEG coat
- Pete will perform optical/electrical checks
- John will perform Gabou map
- Final NEG tube design => media:NEGTUBE_MAY03.pdf
- M20 Old Assembly Modification media:0990.pdf
- M20 New Assembly Can media:0991.pdf
- M20 New Assembly 6.00 x 4.500 reducer flangemedia:0.992.pdf
Gun3 Removal and Diagnostics Chamber Installation
- Second bake and activate week of May 30th => Remove and replace Gun3 ATLIS task
- Remove VBV3I02 from special interlock and swap PLC for relays