Difference between revisions of "October 12, 2016 - 4-Laser/LLRF Monthly Status Meeting"

From Ciswikidb
Jump to navigation Jump to search
 
Line 1: Line 1:
 
'''Agenda'''
 
'''Agenda'''
  
1. Tomasz - LLRF update
+
1. Proposed Installation Schedule [http://opsweb.acc.jlab.org/TJ3/12GeV_CEBAF/WSAD2016.html Winter SAD Schedule]
 
 
2. Software Request to switch laser/LLRF between 250/499 MHz [[media:161012_4Laser4LLRF.docx]]
 
 
 
3. Proposed Installation Schedule [http://opsweb.acc.jlab.org/TJ3/12GeV_CEBAF/WSAD2016.html Winter SAD Schedule]
 
 
* There are ~3 weeks in January for this job: Jan 3 (return to work) to Jan 27 (CEBAF restoration)
 
* There are ~3 weeks in January for this job: Jan 3 (return to work) to Jan 27 (CEBAF restoration)
 
* Week 1 (Jan 4-11) Install LLRF, connect lasers when makes sense, test ability to move between 250/500, verify proper power levels to lasers, and check reproducibility.  
 
* Week 1 (Jan 4-11) Install LLRF, connect lasers when makes sense, test ability to move between 250/500, verify proper power levels to lasers, and check reproducibility.  
 
* Week 2 (Jan 12-18) Injector lock-ups and make e-beam, test against rf sensitive elements like bunchers, chopper, and unit when 2K is restored.
 
* Week 2 (Jan 12-18) Injector lock-ups and make e-beam, test against rf sensitive elements like bunchers, chopper, and unit when 2K is restored.
 
* Week 3 (Jan 19-25) Evaluate and make sure front end is performing well, finalize/rectify outstanding issues, worst case backout.
 
* Week 3 (Jan 19-25) Evaluate and make sure front end is performing well, finalize/rectify outstanding issues, worst case backout.
 +
 +
2. Tomasz - LLRF update
 +
 +
3. Software Request to switch laser/LLRF between 250/499 MHz [[media:161012_4Laser4LLRF.docx]]

Latest revision as of 09:55, 12 October 2016

Agenda

1. Proposed Installation Schedule Winter SAD Schedule

  • There are ~3 weeks in January for this job: Jan 3 (return to work) to Jan 27 (CEBAF restoration)
  • Week 1 (Jan 4-11) Install LLRF, connect lasers when makes sense, test ability to move between 250/500, verify proper power levels to lasers, and check reproducibility.
  • Week 2 (Jan 12-18) Injector lock-ups and make e-beam, test against rf sensitive elements like bunchers, chopper, and unit when 2K is restored.
  • Week 3 (Jan 19-25) Evaluate and make sure front end is performing well, finalize/rectify outstanding issues, worst case backout.

2. Tomasz - LLRF update

3. Software Request to switch laser/LLRF between 250/499 MHz media:161012_4Laser4LLRF.docx