October 12, 2016 - 4-Laser/LLRF Monthly Status Meeting

From Ciswikidb
Revision as of 09:52, 12 October 2016 by Grames (talk | contribs) (Created page with "Agenda 1. Tomasz - LLRF update 2. Software Request to switch laser/LLRF between 250/499 MHz * Request document media:161012_4Laser4LLRF.docx 3. Schedule [http://opsweb....")
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search

Agenda

1. Tomasz - LLRF update

2. Software Request to switch laser/LLRF between 250/499 MHz

3. Schedule Winter SAD Schedule

  • There are ~3 weeks in January for this job: Jan 3 (return to work) to Jan 27 (CEBAF restoration)
  • Week 1 - Install LLRF, connect lasers when makes sense, test ability to move between 250/500, verify proper power levels to lasers, and check reproducibility.
  • Week 2 - Injector lock-ups and make e-beam, test against rf sensitive elements like bunchers, chopper, and unit when 2K is restored.
  • Week 3 - Evaluate and make sure front end is performing well, finalize/rectify outstanding issues, worst case backout.