Difference between revisions of "Sep 08, 2021 - Group Meeting"
Jump to navigation
Jump to search
Line 2: | Line 2: | ||
; | ; | ||
Phase 1 Region | Phase 1 Region | ||
− | * Install 200 kV w/o field emission | + | * (~everyone) Install 200 kV w/o field emission |
− | * Replace DR dipole => PO written week of Aug 30 for new DM at CEBAF, UITF and 2 spare coils | + | * (Lakshmi) Replace DR dipole => PO written week of Aug 30 for new DM at CEBAF, UITF and 2 spare coils |
− | * Replace noisy Wien 20A SCE => | + | * (Sarin/Riad) Replace noisy Wien 20A SCE => |
− | * Repair leaky PCUP LCW fitting | + | * (Phil) Repair leaky PCUP LCW fitting |
− | * Remake A2 joint | + | * (Marcy) Remake A2 joint |
− | * Replace harp | + | * (Marcy) Replace harp |
− | * Install & test 200 kV kicker | + | * (Jerry) Install & test 200 kV kicker |
;Phase 2 Region | ;Phase 2 Region | ||
− | * Possibly install solenoid/valve downstream of chopper => MMF mapping solenoids in Sep. Do we have 2-3/4" pneumatic beam line valve? | + | * (Matt) Possibly install solenoid/valve downstream of chopper => MMF mapping solenoids in Sep. Do we have 2-3/4" pneumatic beam line valve? |
− | * Install bright lighting => Walked area with FM. Waiting for follow-up. | + | * (FM) Install bright lighting => Walked area with FM. Waiting for follow-up. |
===CEBAF 200 kV Gun=== | ===CEBAF 200 kV Gun=== |
Latest revision as of 10:05, 9 September 2021
2022 Winter SAD ATLIS Tasks
Phase 1 Region
- (~everyone) Install 200 kV w/o field emission
- (Lakshmi) Replace DR dipole => PO written week of Aug 30 for new DM at CEBAF, UITF and 2 spare coils
- (Sarin/Riad) Replace noisy Wien 20A SCE =>
- (Phil) Repair leaky PCUP LCW fitting
- (Marcy) Remake A2 joint
- (Marcy) Replace harp
- (Jerry) Install & test 200 kV kicker
- Phase 2 Region
- (Matt) Possibly install solenoid/valve downstream of chopper => MMF mapping solenoids in Sep. Do we have 2-3/4" pneumatic beam line valve?
- (FM) Install bright lighting => Walked area with FM. Waiting for follow-up.
CEBAF 200 kV Gun
- Carlos - Status of small gun HV limits, CEBAF and UITF
- Carlos - GTS gun HV design, i.e. reaching >200 kV w/o field emission
- https://wiki.jlab.org/ciswiki/index.php/18%22_Photogun_ala_GTS
- GTS gun to 280 kV no field emission even with holes in cathode back end
- Gabriel - Picking the anode to eliminate kick