Difference between revisions of "Summer SAD 2015"

From Ciswikidb
Jump to navigation Jump to search
 
(12 intermediate revisions by the same user not shown)
Line 1: Line 1:
== April 3, 2015 - Work Plans ==
+
== April 3, 2015 - Work Plan Ideas ==
 
* Work Plans [[media:SAD15-Summer-CIS.xlsx]]
 
* Work Plans [[media:SAD15-Summer-CIS.xlsx]]
  
Line 10: Line 10:
  
 
== May 14, 2015 - CIS SAD Kickoff Meeting ==
 
== May 14, 2015 - CIS SAD Kickoff Meeting ==
* (Grames) Gun2 Bake History and Planning
+
In broad strokes we'll do all tunnel work between May 18 - July 31.  We'd like brief periods of beam to test Gun2 and Brock during June.  Need to carve out sufficient time for laser and RF work, although summer work only requires 1 laser (499/31).  Final 3 laser should be read by say ~Sep. 1.  The Bubble and Mott occur between Aug 1 and Oct 1.  HCO is mid-Oct, Restoration end of Oct.
 +
 
 +
* Laser work (John)
 +
** Must = analog TEC control, similar seeds for similar pulse width
 +
** Should = improved housing and cooling to diagnose work on lasers
 +
** Like = Phase monitoring for testing purposes
 +
* RF work (Tomasz)
 +
** Must = 3 RF spigots @ 250MHz + 2 RF spigots @ 499MHz
 +
** Should = 360 phase control for all rep rates
 +
** Like = Phase monitoring for testing purposes
 +
* Gun2
 +
** Bake History and Planning (Grames) [[media:150514_Gun2Bake.docx]]
 +
* Brock Cavity
 +
* FC2 Bellows
 +
* Bubble Run
 +
** Installation July 1-31, remove Pavel's cross, restore original beam line, add ANL Bubble chamber
 +
** Engineering run in August/September, ~couple weeks of running Day/Swing
 +
** Laser shuttering needed
 +
* Mott Run
 +
** Run2 in August or September, maybe a long 4 day 24/7 weekend
 +
** No vacuum work planned, will use same gold foils as installed
 +
** Need 31MHz operation, low current <5 uA
 +
* Photocathode Swap (DBR)
 +
 
 +
== May 14, 2015 - Mandatory SAD Kickoff Safety Meeting ==
 +
* CC 1:30pm
 +
 
 +
== May 21, 2015 - Group Meeting ==
 +
* Gun2 Spring 2015 status [[media:150521_Gun2Status.pptx]]

Latest revision as of 09:12, 21 May 2015

April 3, 2015 - Work Plan Ideas

April 26, 2015 - Laser Planning Meeting

May 11, 2015 - Suhring 1330 SAD Scheduling Meeting

May 14, 2015 - CIS SAD Kickoff Meeting

In broad strokes we'll do all tunnel work between May 18 - July 31. We'd like brief periods of beam to test Gun2 and Brock during June. Need to carve out sufficient time for laser and RF work, although summer work only requires 1 laser (499/31). Final 3 laser should be read by say ~Sep. 1. The Bubble and Mott occur between Aug 1 and Oct 1. HCO is mid-Oct, Restoration end of Oct.

  • Laser work (John)
    • Must = analog TEC control, similar seeds for similar pulse width
    • Should = improved housing and cooling to diagnose work on lasers
    • Like = Phase monitoring for testing purposes
  • RF work (Tomasz)
    • Must = 3 RF spigots @ 250MHz + 2 RF spigots @ 499MHz
    • Should = 360 phase control for all rep rates
    • Like = Phase monitoring for testing purposes
  • Gun2
  • Brock Cavity
  • FC2 Bellows
  • Bubble Run
    • Installation July 1-31, remove Pavel's cross, restore original beam line, add ANL Bubble chamber
    • Engineering run in August/September, ~couple weeks of running Day/Swing
    • Laser shuttering needed
  • Mott Run
    • Run2 in August or September, maybe a long 4 day 24/7 weekend
    • No vacuum work planned, will use same gold foils as installed
    • Need 31MHz operation, low current <5 uA
  • Photocathode Swap (DBR)

May 14, 2015 - Mandatory SAD Kickoff Safety Meeting

  • CC 1:30pm

May 21, 2015 - Group Meeting