− | == '''Run Plan for April 15''' == | + | == '''Run Plan for April 15-16''' == |
* Day shift. Control access | * Day shift. Control access | ||
− | * Repair beam viewer camera, FTOF HV , DC gas. | + | * Repair beam viewer camera, FTOF HV , DC gas. DONE |
− | * Change SVT filters. Switch off solenoid for that. | + | * Change SVT filters. Switch off solenoid for that. DONE |
− | * Check RF signals | + | * Check RF signals DONE |
− | * Change the Torus polarity | + | * Change the Torus polarity DONE |
− | * Moller runs with the helicity delayed reporting | + | * Moller runs with the helicity delayed reporting DONE |
− | * | + | * Empty targer DONE |
− | + | <font color=blue> | |
+ | * Empty tagger run with trigger_v12_3.trg @150 nA - 4 hours | ||
+ | * Fill targer (Follow instruction, in case of problems call PDL and engineering on call) | ||
+ | * Start production with trigger_v12_3.trg @ 50nA | ||
+ | </font> | ||
* If the machine is down for few hours ask for low current first 5 nA make sure that the beam is stable both in position and current, check that the rates are OK on all the detectors and halo counters. Then ask for 45 nA and continue data for production. If there are issues with the beam call the RC. | * If the machine is down for few hours ask for low current first 5 nA make sure that the beam is stable both in position and current, check that the rates are OK on all the detectors and halo counters. Then ask for 45 nA and continue data for production. If there are issues with the beam call the RC. | ||
Revision as of 21:24, 16 April 2018
Shift ScheduleShift ChecklistHot CheckoutBeam Time Accounting
|
Manuals |
Procedures |
JLab Logbooks
|
If calling local numbers (with area code prefix 757) from the counting room dial 9+[last 7 digits]. To call other area codes dial 91+[10 digit number]
|
|
- Note, all non-JLab numbers must be dialed with an area code. When calling from a counting-house landline, dial "9" first.
- To call JLab phones from outside the lab, all 4-digit numbers must be preceded by 757-269
- Click Here to edit Phone Numbers. Note, you then also have to edit the current page to force a refresh.
Click Here to edit Phone Numbers. Note, you then also have to edit this page to force a refresh.
CLAS12 Run Group A, Spring 2018
Beam energy 10.6 GeV (5 pass)
Important: Document all your work in the logbook!
Remember to fill in the run list at the beginning and end of each run (clas12run@gmail.com can fill the run list)
RC: Valery Kubarovsky
- (757) 575-7540
- 9 575 7540 from Counting Room
- vpk@jlab.org
PDL: Eugene Pasyuk
- (757) 876-1789
- 9 876-1789 from Counting Room
- pasyuk@jlab.org
- Note 1: Be very mindful of the background rates in the halo counters, rates in the detectors, and currents in the SVT for all settings to ensure that they are at safe levels.
The UPSTREAM rate jhas to be in the range 0-15 and MIDSTREAM has to be in the rage 10-20 @45 nA. Count rates in the range of tens or more may indicate bad beam tune or bleed-through from other Halls.
- Note 2: At the end of each run, follow the DAQ restart sequence
"end run", "cancel", "reset", "Configure", "download", "prestart", "iocjscalerRestartAll.sh", "go".
After DAQ prestart is complete reboot the scaler IOCs with the command: iocjscalerRestartAll.sh.
Note: After each step, make sure it is complete in the Run Control message window. If a roc has crashed, find which one it is and issue a roc_reboot command and try again. Contact the DAQ expert if there are any questions.
- Note 3: Nominal beam positions: 2C24A (X=0.5,Y=0.5) , 2H01 (X=1.0 mm, Y=-1.5 mm) see log entry https://logbooks.jlab.org/entry/3560786.
- Note 5: In case of the Torus and/or Solenoid Fast Dump do the following:
- Notify MCC, request beam OFF and drop Hall status to Power Permit
- Call Engineering on-call
- Make separate log entry with copies to HBTORUS and HBSOLENOID logbooks. In the "Notify" filed add Ruben Fair, Probir Goshal, Dave Kashy and esr-users@jlab.org
- Notify Run Coordinator
- Call the MM expert to turn the detector off
- Call SVT expert to turn SVT off
- Turn off all the other detectors
Run Plan:(last update 4/11 - 10:30)
Run Plan for April 15-16
In case of other questions or uncertainties of what to do, please call the RC
|
General Instructions:
Every Shift:
Every Run: Log screenshots of:
|
Webcams |
Manuals |
Epics on the web
|
Hall-B
Run lists |
Accelerator |
Bluejean meetings
|