== Establish beam to the tagger dump == | == Establish beam to the tagger dump == | ||
− | # See | + | # See [[Media:CLAS12_beamline_commissioning.pdf|Beamline Commissioning Plans]], execute 2(a) to 2(g). |
# Log screenshots of the ECal and main HPS scaler screens for reference when beam is established at the tagger | # Log screenshots of the ECal and main HPS scaler screens for reference when beam is established at the tagger | ||
== Bring beam to FC: == | == Bring beam to FC: == |
Revision as of 17:38, 29 January 2017
[edit]
Shift ScheduleShift ChecklistHot CheckoutBeam Time Accounting |
Manuals |
Procedures |
JLab Logbooks
|
|
|
- Note, all non-JLab numbers must be dialed with an area code. When calling from a counting-house landline, dial "9" first.
- To call JLab phones from outside the lab, all 4-digit numbers must be preceded by 757-269
- Click Here to edit Phone Numbers. Note, you then also have to edit the current page to force a refresh.
Click Here to edit Phone Numbers. Note, you then also have to edit this page to force a refresh.
CLAS12 KPP run, February 3 to March 3
Beam energy 6.4 GeV (3 pass)
Important: Document all your work in the logbook!
RC: Stepan Stepanyan
- (757) 575-7540
- 9 575 7540 from Counting Room
PDL: Eugene Pasyuk
- (757) 876-1789
- 9 876-1789 from Counting Room
Run Plan for February 2 - 3, 2017 :Start close-up of the Hall at 3pm on Friday, February 3Locking up the hall on Fridays
Establish beam to the tagger dump
Bring beam to FC:
Important Notes:
|
General Instructions:DAQ RECOVERYIf DAQ crashed/broken:
Establishing Acceptable Beam Conditions:
Note: in order to have reliable readings on two important for HPS BPMs, 2H00 and 2H02, beam current should be >30 nA.
Setting up the FSD threshold
hpsrun@clonpc11> /home/hpsrun/scripts/FSD/Calc_FSD_Threshold.exe
|
Every Shift:
|
Every Run:
|
---|