Difference between revisions of "KPP Run"
Jump to navigation
Jump to search
Line 108: | Line 108: | ||
# Switch to 6-sector trigger (some time ~11pm), take data till Monday morning. | # Switch to 6-sector trigger (some time ~11pm), take data till Monday morning. | ||
# <b> Run ends 7 am on Monday. Following has to be done: | # <b> Run ends 7 am on Monday. Following has to be done: | ||
− | #* End the run, turn OFF HVs for all detectors | + | #* End the run, turn OFF HVs for all detectors, Start Ramping torus down to zero |
− | #* Retract the target using 2H01 expert GUI, just put -10 in the left "MoveAbs" and hit the return. Motor will go towards 0, and will hit "Lo Limit" limit switch | + | #* Retract the target using 2H01 expert GUI, just put -10 in the left "MoveAbs" and hit the return. Motor will go towards 0, and will hit "Lo Limit" limit switch |
− | |||
#* Ask MCC to change beam current to 50nA with small steps, this is to calibrate SLM (data goes to MYA, but you can record beam current and the SLM reading if you want) | #* Ask MCC to change beam current to 50nA with small steps, this is to calibrate SLM (data goes to MYA, but you can record beam current and the SLM reading if you want) | ||
#* When finished, got to 50nA, ask MCC to terminate the beam and take the Hall to restricted access. | #* When finished, got to 50nA, ask MCC to terminate the beam and take the Hall to restricted access. |
Revision as of 23:30, 5 February 2017
[edit]
|
|
- Note, all non-JLab numbers must be dialed with an area code. When calling from a counting-house landline, dial "9" first.
- To call JLab phones from outside the lab, all 4-digit numbers must be preceded by 757-269
- Click Here to edit Phone Numbers. Note, you then also have to edit the current page to force a refresh.
Click Here to edit Phone Numbers. Note, you then also have to edit this page to force a refresh.
CLAS12 KPP run, February 3 to March 3
Beam energy 6.4 GeV (3 pass)
Important: Document all your work in the logbook!
RC: Stepan Stepanyan
- (757) 575-7540
- 9 575 7540 from Counting Room
PDL: Eugene Pasyuk
- (757) 876-1789
- 9 876-1789 from Counting Room
Run Plan for February 4-5, 2017 :
Plan:
Important Notes:
|
General Instructions:Locking up the hall
Establishing Acceptable Beam Conditions:
Setting up the FSD threshold
hpsrun@clonpc11> /home/hpsrun/scripts/FSD/Calc_FSD_Threshold.exe
|
Every Shift:
|
Every Run:
|
---|
Webcams |
Manuals |
Epics on the web
|