== <font color=blue>''' Run Plan:'''</font>== | == <font color=blue>''' Run Plan:'''</font>== | ||
− | |||
* <s>The first task when beam is available is to tune the beam to the tagger magnet yoke dump. Follow the instructions under the "Procedures" link on the Run Info wikipage for setting up the beam (see the [https://wiki.jlab.org/clas12-run/images/7/74/CLAS12_beamline_commissioning.pdf instructions] for setting up the beam). See the reference harp scans for 2C21 and 2C24 (tagger harp) under the beam tuning section. The beamline expert should be present for this portion of the run plan. This work is as specified in the Commissioning Run Plan [https://www.jlab.org/Hall-B/calcom/cwb-erun.pdf Phase 1 Step #1].</s> | * <s>The first task when beam is available is to tune the beam to the tagger magnet yoke dump. Follow the instructions under the "Procedures" link on the Run Info wikipage for setting up the beam (see the [https://wiki.jlab.org/clas12-run/images/7/74/CLAS12_beamline_commissioning.pdf instructions] for setting up the beam). See the reference harp scans for 2C21 and 2C24 (tagger harp) under the beam tuning section. The beamline expert should be present for this portion of the run plan. This work is as specified in the Commissioning Run Plan [https://www.jlab.org/Hall-B/calcom/cwb-erun.pdf Phase 1 Step #1].</s> | ||
* Following beam tuning to the tagger magnet yoke, complete a series of Moller polarimeter run. The beamline expert should be present for this portion of the run plan. This work is as specified in the Commissioning Run Plan [https://www.jlab.org/Hall-B/calcom/cwb-erun.pdf Phase 1 Step #2]. | * Following beam tuning to the tagger magnet yoke, complete a series of Moller polarimeter run. The beamline expert should be present for this portion of the run plan. This work is as specified in the Commissioning Run Plan [https://www.jlab.org/Hall-B/calcom/cwb-erun.pdf Phase 1 Step #2]. |
Revision as of 13:22, 12 January 2018
[edit]
Shift ScheduleShift ChecklistHot CheckoutBeam Time Accounting |
Manuals |
Procedures |
JLab Logbooks
|
|
|
- Note, all non-JLab numbers must be dialed with an area code. When calling from a counting-house landline, dial "9" first.
- To call JLab phones from outside the lab, all 4-digit numbers must be preceded by 757-269
- Click Here to edit Phone Numbers. Note, you then also have to edit the current page to force a refresh.
Click Here to edit Phone Numbers. Note, you then also have to edit this page to force a refresh.
CLAS12 Engineering Run, Winter 2018
Beam energy 10.6 GeV (5 pass)
Important: Document all your work in the logbook!
Remember to fill in the run list at the beginning and end of each run (clas12run@gmail.com can fill the run list)
RC: Daniel S. Carman
- (757) 575-7540
- 9 575 7540 from Counting Room
- carman@jlab.org
PDL: Eugene Pasyuk
- (757) 876-1789
- 9 876-1789 from Counting Room
- pasyuk@jlab.org
- Note 1: Due to issues with the gas handling system with the MM trackers (BMT, FMT, FT-Trk), the HV should be left off but the LV should be turned on.
- Note 2: Be very mindful of the background rates in the halo counters, rates in the detectors, and currents in the SVT for all settings to ensure that they are at safe levels.
- Note 3: At the end of each run, follow the DAQ restart sequence "end run", "abort", "reset", "download", "prestart", "go". The DAQ rate should be 2 -3 kHz (this includes a 1 kHz pulser). After DAQ prestart is complete reboot the scaler IOCs with the command: iocjscalerRestartAll.sh. Note: After each step, make sure it is complete in the Run Control message window. If a roc has crashed, find which one it is and issue a roc_reboot command and try again. Contact the DAQ expert if there are any questions.
- Note 4: Record forces on torus and solenoid sensors in configuration with torus at full field and solenoid at zero field.
- Note 5: When possible during a day time access, call Jennifer Williams to do a magnetic field survey in the hall with torus and solenoid at full field.
Run Plan:
|
General Instructions:
Beam Tuning:
When ready to get beam, Turn all beamline devices ON, turn all CLAS12 detectors OFF (including SVT)
|
Every Shift:
|
Every Run:
|
---|
Webcams |