Difference between revisions of "Engineering Run"
Jump to navigation
Jump to search
Line 106: | Line 106: | ||
* Continue detector turn on now for the DC, CTOF, CND, and SVT - contacting the subsystem teams to perform this work. Record rates and current for all detectors in the logbook. This work is as specified in the Commissioning Run Plan [https://www.jlab.org/Hall-B/calcom/cwb-erun.pdf Phase 1 Step #6]. | * Continue detector turn on now for the DC, CTOF, CND, and SVT - contacting the subsystem teams to perform this work. Record rates and current for all detectors in the logbook. This work is as specified in the Commissioning Run Plan [https://www.jlab.org/Hall-B/calcom/cwb-erun.pdf Phase 1 Step #6]. | ||
* Begin initial DAQ and trigger checkout to re-establish the DAQ and basic electron trigger from the Dec. 2017 run. This work will be led by the DAQ and trigger experts. This work is as specified in the Commissioning Run Plan [https://www.jlab.org/Hall-B/calcom/cwb-erun.pdf Phase 1 Step #7]. | * Begin initial DAQ and trigger checkout to re-establish the DAQ and basic electron trigger from the Dec. 2017 run. This work will be led by the DAQ and trigger experts. This work is as specified in the Commissioning Run Plan [https://www.jlab.org/Hall-B/calcom/cwb-erun.pdf Phase 1 Step #7]. | ||
− | * | + | * Begin solenoid rate studies and luminosity scans: |
− | * | + | ** <b> The following studies involve all CLAS12 detector subsystems (except the MM trackers) and should be supported by all subsystem experts.</b> |
− | * Work on optimizing the electron trigger. This work will be led by the trigger team. This work is as specified in the Commissioning Run Plan [https://www.jlab.org/Hall-B/calcom/cwb-erun.pdf Phase 1 Step #10]. | + | ** With a beam current of 10 nA, study the detector rates and currents for all subsystems, as well as DC occupancies for solenoid field settings of 100%, 90%, 80%, 70%, 60%, 50%. Record all information in the logbook. Record scalers with EPICS scaler dump tool. This work is as specified in the Commissioning Run Plan [https://www.jlab.org/Hall-B/calcom/cwb-erun.pdf Phase 1 Step #11]. |
− | + | ** Perform luminosity scan at currents of 10 nA, 25 nA, 50 nA, 75 nA, 100 nA, 120 nA. For each setting, record the rates and currents for all subsystems, as well as DC occupancies. Record all information in the logbook. Record scalers with EPICS scaler dump tool. This work is as specified in the Commissioning Run Plan [https://www.jlab.org/Hall-B/calcom/cwb-erun.pdf Phase 1 Step #12]. | |
+ | * Take calibration runs with FT-Off - contact DAQ expert for assistance with running DAQ system | ||
+ | ** Take calibration data for 4 hours at 20 nA. | ||
+ | ** Take calibration data for 4 hours at 50 nA | ||
+ | ** This work is as specified in the Commissioning Run Plan [https://www.jlab.org/Hall-B/calcom/cwb-erun.pdf Phase 1 Step #13]. | ||
+ | ** Carefully monitor beam tune to be sure that it is stable. Contact MCC immediately if the tune goes bad. Contact the beamline expert if there are questions regarding the beam tuning. | ||
+ | * Longer term plans: | ||
+ | ** Work on detector setup optimization steps to set DC readout windows for R1, R2, and R3, and the PMT-based detector TDC readout windows to match the FADC windows. This work will be led by the DAQ expert in conjunction with the subsystem experts. This work is as specified in the Commissioning Run Plan [https://www.jlab.org/Hall-B/calcom/cwb-erun.pdf Phase 1 Step #8]. | ||
+ | ** Work on optimizing the electron trigger. This work will be led by the trigger team. This work is as specified in the Commissioning Run Plan [https://www.jlab.org/Hall-B/calcom/cwb-erun.pdf Phase 1 Step #10]. | ||
+ | |||
| valign=top | | | valign=top | |
Revision as of 16:03, 12 January 2018
[edit]
Shift ScheduleShift ChecklistHot CheckoutBeam Time Accounting |
Manuals |
Procedures |
JLab Logbooks
|
|
|
- Note, all non-JLab numbers must be dialed with an area code. When calling from a counting-house landline, dial "9" first.
- To call JLab phones from outside the lab, all 4-digit numbers must be preceded by 757-269
- Click Here to edit Phone Numbers. Note, you then also have to edit the current page to force a refresh.
Click Here to edit Phone Numbers. Note, you then also have to edit this page to force a refresh.
CLAS12 Engineering Run, Winter 2018
Beam energy 10.6 GeV (5 pass)
Important: Document all your work in the logbook!
Remember to fill in the run list at the beginning and end of each run (clas12run@gmail.com can fill the run list)
RC: Daniel S. Carman
- (757) 575-7540
- 9 575 7540 from Counting Room
- carman@jlab.org
PDL: Eugene Pasyuk
- (757) 876-1789
- 9 876-1789 from Counting Room
- pasyuk@jlab.org
- Note 1: Due to issues with the gas handling system with the MM trackers (BMT, FMT, FT-Trk), the HV should be left off but the LV should be turned on.
- Note 2: Be very mindful of the background rates in the halo counters, rates in the detectors, and currents in the SVT for all settings to ensure that they are at safe levels.
- Note 3: At the end of each run, follow the DAQ restart sequence "end run", "abort", "reset", "download", "prestart", "go". The DAQ rate should be 2 -3 kHz (this includes a 1 kHz pulser). After DAQ prestart is complete reboot the scaler IOCs with the command: iocjscalerRestartAll.sh. Note: After each step, make sure it is complete in the Run Control message window. If a roc has crashed, find which one it is and issue a roc_reboot command and try again. Contact the DAQ expert if there are any questions.
- Note 4: Record forces on torus and solenoid sensors in configuration with torus at full field and solenoid at zero field.
- Note 5: When possible during a day time access, call Jennifer Williams to do a magnetic field survey in the hall with torus and solenoid at full field.
Run Plan:
|
General Instructions:
Beam Tuning:
When ready to get beam, Turn all beamline devices ON, turn all CLAS12 detectors OFF (including SVT)
|
Every Shift:
|
Every Run:
|
---|