Difference between revisions of "Engineering Run"
Jump to navigation
Jump to search
Line 105: | Line 105: | ||
** Carefully monitor beam tune to be sure that it is stable. Contact MCC immediately if the tune goes bad. Contact the beamline expert if there are questions regarding the beam tuning.</s> | ** Carefully monitor beam tune to be sure that it is stable. Contact MCC immediately if the tune goes bad. Contact the beamline expert if there are questions regarding the beam tuning.</s> | ||
* Begin luminosity scan and solenoid rate studies: | * Begin luminosity scan and solenoid rate studies: | ||
− | ** Perform luminosity scan at currents of 0 nA, 10 nA, <s>25 nA</s>, <s>50 nA</s>, <s>75 nA</s>, 100 nA, | + | ** Perform luminosity scan at currents of 0 nA, 10 nA, <s>25 nA</s>, <s>50 nA</s>, <s>75 nA</s>, 100 nA, 125 nA, 150 nA using a random trigger. For each setting, record the rates and currents for all subsystems, as well as DC occupancies. Record all information in the logbook. This work is as specified in the Commissioning Run Plan [https://www.jlab.org/Hall-B/calcom/cwb-erun.pdf Phase 1 Step #12]. The Run Coordinator will determine the safe current limit for CLAS12 and the beamline expert will specify the FSD trip levels. Do not go beyond 75 nA without consulting the Run Coordinator. DC time windows should be 250 ns (R1), 500 ns (R2), 750 ns (R3). |
** With a beam current of 10 nA, study the detector rates and currents for all subsystems, as well as DC occupancies for solenoid field settings of 100%, 90%, 80%, 70%, 60%, 50%. Record all information in the logbook. This work is as specified in the Commissioning Run Plan [https://www.jlab.org/Hall-B/calcom/cwb-erun.pdf Phase 1 Step #11]. | ** With a beam current of 10 nA, study the detector rates and currents for all subsystems, as well as DC occupancies for solenoid field settings of 100%, 90%, 80%, 70%, 60%, 50%. Record all information in the logbook. This work is as specified in the Commissioning Run Plan [https://www.jlab.org/Hall-B/calcom/cwb-erun.pdf Phase 1 Step #11]. | ||
* Work on trigger development studies and detector optimization. Contact the DAQ and trigger experts to lead this effort. This work is as specified in the Commissioning Run Plan [https://www.jlab.org/Hall-B/calcom/cwb-erun.pdf Phase 1 Step #10]. | * Work on trigger development studies and detector optimization. Contact the DAQ and trigger experts to lead this effort. This work is as specified in the Commissioning Run Plan [https://www.jlab.org/Hall-B/calcom/cwb-erun.pdf Phase 1 Step #10]. |
Revision as of 11:51, 13 January 2018
[edit]
Shift ScheduleShift ChecklistHot CheckoutBeam Time Accounting |
Manuals |
Procedures |
JLab Logbooks
|
|
|
- Note, all non-JLab numbers must be dialed with an area code. When calling from a counting-house landline, dial "9" first.
- To call JLab phones from outside the lab, all 4-digit numbers must be preceded by 757-269
- Click Here to edit Phone Numbers. Note, you then also have to edit the current page to force a refresh.
Click Here to edit Phone Numbers. Note, you then also have to edit this page to force a refresh.
CLAS12 Engineering Run, Winter 2018
Beam energy 10.6 GeV (5 pass)
Important: Document all your work in the logbook!
Remember to fill in the run list at the beginning and end of each run (clas12run@gmail.com can fill the run list)
RC: Daniel S. Carman
- (757) 575-7540
- 9 575 7540 from Counting Room
- carman@jlab.org
PDL: Eugene Pasyuk
- (757) 876-1789
- 9 876-1789 from Counting Room
- pasyuk@jlab.org
- Note 1: Leave the HV to the FMT off until further notice.
- Note 2: Be very mindful of the background rates in the halo counters, rates in the detectors, and currents in the SVT for all settings to ensure that they are at safe levels.
- Note 3: At the end of each run, follow the DAQ restart sequence "end run", "abort", "reset", "download", "prestart", "go". The DAQ rate should be 2 -3 kHz (this includes a 1 kHz pulser). After DAQ prestart is complete reboot the scaler IOCs with the command: iocjscalerRestartAll.sh. Note: After each step, make sure it is complete in the Run Control message window. If a roc has crashed, find which one it is and issue a roc_reboot command and try again. Contact the DAQ expert if there are any questions.
- Note 4: Record forces on torus and solenoid sensors in configuration with torus at full field and solenoid at zero field.
- Note 5: When possible during a day time access, call Jennifer Williams to do a magnetic field survey in the hall with torus and solenoid at full field.
Run Plan:
|
General Instructions:
Beam Tuning:
When ready to get beam, Turn all beamline devices ON, turn all CLAS12 detectors OFF (including SVT)
|
Every Shift:
|
Every Run:
|
---|
Webcams |
Manuals |
Epics on the web
|