Line 118: | Line 118: | ||
* At 7:00 am MVT expert will come to take a run without gas flow, it will be dedicated run of 15-20 mn--> | * At 7:00 am MVT expert will come to take a run without gas flow, it will be dedicated run of 15-20 mn--> | ||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
+ | <font color=blue>''' Plan for February 13 '''</font> | ||
+ | |||
+ | * Beam estaliched to the FC | ||
+ | * All detector On | ||
+ | * Put beam blocker in | ||
+ | * Ask MCC for 30nA | ||
+ | * Take short run check that all the rates are Ok on all detectos | ||
+ | * Once everything stable ask MCC for 50 nA and start taking data with empty target for 2 hours/run with the RGA trigger configuration elec_htcc_1phe_pcal_300.trg and PROD configuration file. | ||
+ | * At 6 am give the DAQ to Andrea to perform FT Trigger studies | ||
+ | * At 8:30 Bob will fill the target | ||
+ | * At 9:30 once the target is full Valery, Sergey and Ben will take over to set/adjust the trigger parameter | ||
+ | |||
+ | |||
+ | <!-- | ||
'''[[Every Shift:]]''' | '''[[Every Shift:]]''' | ||
*Follow run plan as outlined by RC | *Follow run plan as outlined by RC | ||
Line 159: | Line 149: | ||
* Beam strip charts | * Beam strip charts | ||
− | + | --> | |
| valign=top | | | valign=top | | ||
Revision as of 01:58, 13 February 2018
[edit]
Shift ScheduleShift ChecklistHot CheckoutBeam Time Accounting |
Manuals |
Procedures |
JLab Logbooks
|
|
|
- Note, all non-JLab numbers must be dialed with an area code. When calling from a counting-house landline, dial "9" first.
- To call JLab phones from outside the lab, all 4-digit numbers must be preceded by 757-269
- Click Here to edit Phone Numbers. Note, you then also have to edit the current page to force a refresh.
Click Here to edit Phone Numbers. Note, you then also have to edit this page to force a refresh.
CLAS12 Run Group A, Winter 2018
Beam energy 10.6 GeV (5 pass)
Important: Document all your work in the logbook!
Remember to fill in the run list at the beginning and end of each run (clas12run@gmail.com can fill the run list)
RC: Latifa Elouadrhiri
- (757) 575-7540
- 9 575 7540 from Counting Room
- latifa@jlab.org
PDL: Eugene Pasyuk
- (757) 876-1789
- 9 876-1789 from Counting Room
- pasyuk@jlab.org
- Note 1: Be very mindful of the background rates in the halo counters, rates in the detectors, and currents in the SVT for all settings to ensure that they are at safe levels.
- Note 2: At the end of each run, follow the DAQ restart sequence "end run", "abort", "reset", "download", "prestart", "go". After DAQ prestart is complete reboot the scaler IOCs with the command: iocjscalerRestartAll.sh. Note: After each step, make sure it is complete in the Run Control message window. If a roc has crashed, find which one it is and issue a roc_reboot command and try again. Contact the DAQ expert if there are any questions.
- Note 3: Nominal beam positions: 2C21 (X=0.0 mm, Y=0.0 mm), 2C24 (X=0.0 mm, Y=0.7 mm), 2H01 (X=0.3 mm, Y=-0.6 mm)
- Note 4: With beam to the Faraday Cup, typical rates on all halo counters upstream from the target should be either 0 or of the order of few counts. Count rates in the range of tens or more may indicate bad beam tune or bleed-through from other Halls.
Run Plan:(last update 2/12- 12:00)
Plan for February 13
|
General Instructions:
Every Shift:
|