Line 104: | Line 104: | ||
* <s>Once all detectors are on, record rates in all detectors, and currents in the DC, SVT, and MM, at solenoid field settings of 50%, 60%, 70%, 80%, 90%, and 100%. To do that use the tool described at https://logbooks.jlab.org/entry/3504609. Make sure that the logbook information is complete and readable!</s> | * <s>Once all detectors are on, record rates in all detectors, and currents in the DC, SVT, and MM, at solenoid field settings of 50%, 60%, 70%, 80%, 90%, and 100%. To do that use the tool described at https://logbooks.jlab.org/entry/3504609. Make sure that the logbook information is complete and readable!</s> | ||
* <s>At full solenoid field, take 30 min of data at 5 nA.</s> | * <s>At full solenoid field, take 30 min of data at 5 nA.</s> | ||
− | * At 100% solenoid field, record rates in all detectors, and currents in the DC, SVT, and MM, at beam currents of 5 nA, 15 nA, 25 nA, ... The beam intensity and duration will be established by the beamline expert and the SVT and MM experts. Make sure that the logbook information is complete and readable! If the DC currents are too high and there are too many trips, the HV may have to be reduced to setting #9 or #8. | + | * At 100% solenoid field, record rates in all detectors, and currents in the DC, SVT, and MM, at beam currents of 5 nA, 15 nA, 25 nA, ... The beam intensity and duration will be established by the beamline expert and the SVT and MM experts. Make sure that the logbook information is complete and readable! If the DC currents are too high and there are too many trips, the HV may have to be reduced to setting #9 or #8 (see log entry for instructions at https://logbooks.jlab.org/entry/3503848. |
* At the highest beam current, follow the instructions at https://logbooks.jlab.org/entry/3504610 to run the HTCC delay scan script. | * At the highest beam current, follow the instructions at https://logbooks.jlab.org/entry/3504610 to run the HTCC delay scan script. | ||
* At 100% solenoid field take 30 min of data at the highest current authorized by the SVT/MM folks (ensuring that the DC and other detector currents/rates are acceptable). Select the trigger file based on high threshold ECAL clusters (to select electrons). Contact the DAQ expert to set this up. | * At 100% solenoid field take 30 min of data at the highest current authorized by the SVT/MM folks (ensuring that the DC and other detector currents/rates are acceptable). Select the trigger file based on high threshold ECAL clusters (to select electrons). Contact the DAQ expert to set this up. |
Revision as of 02:44, 15 December 2017
[edit]
Shift ScheduleShift ChecklistHot CheckoutBeam Time Accounting |
Manuals |
Procedures |
JLab Logbooks
|
|
|
- Note, all non-JLab numbers must be dialed with an area code. When calling from a counting-house landline, dial "9" first.
- To call JLab phones from outside the lab, all 4-digit numbers must be preceded by 757-269
- Click Here to edit Phone Numbers. Note, you then also have to edit the current page to force a refresh.
Click Here to edit Phone Numbers. Note, you then also have to edit this page to force a refresh.
CLAS12 Engineering Run, Fall 2017
Beam energy 10.6 GeV (5 pass)
Torus : +3770 A (100% field);
Important: Document all your work in the logbook!
Remember to fill in the run list at the beginning and end of each run (clas12run@gmail.com can fill the run list)
RC: Daniel S. Carman
- (757) 575-7540
- 9 575 7540 from Counting Room
- carman@jlab.org
PDL: Eugene Pasyuk
- (757) 876-1789
- 9 876-1789 from Counting Room
- pasyuk@jlab.org
Run Plan:All studies for the next few shifts will use 100% torus field (negatives bending in); the strength of the solenoid field and the status of the hydrogen target are listed below.
|
General Instructions:
Beam Tuning:
When ready to get beam, Turn all beamline devices ON, turn all CLAS12 detectors OFF (including SVT)
|
Every Shift:
|
Every Run:
|
---|
Webcams |