Difference between revisions of "Run Group C"
Line 37: | Line 37: | ||
| valign=top | | | valign=top | | ||
===Procedures=== | ===Procedures=== | ||
− | * [https://github.com/JeffersonLab/clas12-manuals/raw/master/beamline/manual/ | + | * [https://github.com/JeffersonLab/clas12-manuals/raw/master/beamline/manual/beam_estab_rgm.pdf Physics-Quality Beam] |
* [[Media:moller.pdf|Performing Møller Runs]] | * [[Media:moller.pdf|Performing Møller Runs]] | ||
* [[Media:HarpScanManual.pdf|Performing Harp Scans]] | * [[Media:HarpScanManual.pdf|Performing Harp Scans]] |
Revision as of 12:24, 7 June 2022
- Shift Documentation
- Phone Numbers
- Short Term Schedule
- Shift Expert
- Remote Worker Shift
- Monitoring
- Useful Links
Shift ScheduleHall B LogbookESAD, COO, RSADShift ChecklistHot CheckoutBeam Time Accounting
|
Manuals
|
Procedures |
JLab Logbooks
|
|
|
- Note, all non-JLab numbers must be dialed with an area code. When calling from a counting-house landline, dial "9" first.
- To call JLab phones from outside the lab, all 4-digit numbers must be preceded by 757-269
- Click Here to edit Phone Numbers. Note, you then also have to edit the current page to force a refresh.
Click Here to edit Phone Numbers. Note, you then also have to edit the current page to force a refresh.
CLAS12 Run Group C, Summer 2022
Daily RC Meetings at 14:00: CH Room 200C, and on Zoom
Zoom information: Link, Meeting ID: 160 867 4253, Passcode: 786506
RC: Sebastian Kuhn
- 757 575-7540 or
- 757 639-6640
- Dial "9" before all numbers when calling from CH
PDL: Eugene Pasyuk
- (9-)757 876-1789 , x6020 office
Run Coordinator and Target Expert Schedule
Longterm Run Plan
IMPORTANT NOTE: Before leaving the hall and going to beam permit check that dome lights, froward carriage lights, and pie tower lights are OFF
Run Plan: June 2022
- Tue, 6/7: Complete beam line; Hall closes up at 3:00 for beam line magnet tests
- Wed, 6/8: Finish all surveys and alignments, calibrate BPMs. Test target samples (TE, polarize). Check out raster.
- Thu, 6/9: Continue HCO for all components, target polarization / swap tests. Install cross-hair target probe for beam. If ready, close Hall and get ready for beam.
- Fri, 6/10: If possible, tune 1-pass beam to FC. Begin commissioning and raster calibration
- Weekend: Take data with MT, 12C and polarized NH3 targets.
- Early next week: If time allows, take data on CH2, CD2 and polarized ND3.
- Then change from 1-pass to 5 pass.
1-pass (2.1 GeV) Running conditions
- Establish optimal compromise between raster size (if possible, 7 mm radius), luminosity (goal: 5 nA), and background.
- Run duration 100M events or 4 hours, whichever comes first.
- For empty target runs, increase beam current as much as possible (up to 50 nA).
DAQ configuration
- Configuration TBA, trigger file rgc_100MeV_V1.0_no_DC.trg
- NOTE: UNLESS a RICH problem crashes the DAQ, do NOT interrupt an otherwise smooth run to do a RICH recovery - instead do this in between runs.
- NOTE: BOTH the shift expert AND the shift worker MUST check monitoring histograms at least once every 30-60 minutes to make sure there are no major detector problems.Watch the raster pattern!
- At the end of each run, follow the STANDARD DAQ RESTART SEQUENCE:
- "end run", if the run ended correctly then: "prestart", "go"
- if the run did not end correctly or if any ROCs had to be rebooted:
- "cancel", "reset"
- "configure", "download", "prestart", "go"
- After each step, make sure it is completed in the Run Control message window. If a ROC has crashed, find which one it is, issue a roc_reboot command ON JUST THAT ROC and try again. Contact the DAQ expert if there are any questions.
References and Standards
Solenoid set-point of 2417.5 A results in read back 2419.57 A and exactly 5.00 T field on center
Nominal Beam Positions
- 2H01, X: ? mm, Y: ? mm (only used/useful without restoring)
- 2C24, X: -? mm, Y: ? mm (orbit lock)
FSD Thresholds (to be updated)
- Upstream: 2000 Hz
- Midstream: 2000 Hz
- Downstream: 500000 Hz
- BOM: 10000
- 5 ms dwell time
Reference Harp Scans for Beam on Faraday Cup 2H01 [1]
Reference Harp Scans for Beam on Tagger dump 2C21 [2], tagger harp [3]
Reference Monitoring Histograms
Counter rates
- Upstream counters integrated rates: 0-15 Hz (acceptable up to 100 Hz are acceptable) @50 nA.
- Midstream counters: 10-20 Hz (acceptable up to 50 Hz) @50 nA.
- Counting rates of ~ hundreds of Hz may indicate bad beam tune or bleed-through from other Halls.
NOTE: BOTH the shift expert AND the shift worker MUST check monitoring histograms at least once every 30 - 60 minutes to make sure there are no major detector problems.
(remote) shift worker: see dedicated Remote Shifts tab above. |
TasksEvery Run:
Every Shift:
Regularly:
|
|
Webcams
|
Manuals |
Epics on the web
|
Live Monitoring Links |
Hall-B |
Accelerator |
ZOOM meetings
|